Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): BGE Inc.
MWBE Contracted Goal (if applicable): 11.316%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a Professional Services Agreement with BGE Inc. for Construction Phase Services in the amount of $249,573.00 in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 11.316%.
end
Background and Discussion:
The project is located in Baytown, TX, approximately 1.2 miles south of Interstate Highway 10 and 0.1 miles west of the Harris County line. Cedar Bayou Park East and West drains by roadside ditches with some intermittent storm sewers. The major drainage system collector is Harris County Flood Control District (HCFCD) channel Q13-00-00 which drains the neighborhood from Sjolander to the outfall location at Bayou Boulevard. The proposed improvements in the subdivision are to regrade roadside ditches, install storm sewer beneath ditches, construct driveways and driveway culverts, and construct a storm water detention basin. The additional funds will cover the construction phase services agreement to allow for construction oversight of the project.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the C...