Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 24104MF39201
Vendor/Entity Legal Name (if applicable): Mission Bend Municipal Utility District No. 2
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal agreement with Mission Bend Municipal Utility District No. 2 for drainage improvements to the pedestrian bridge in and around Magnolia Park and Mission Bend Greenbelt trails and all related appurtenances, Interlocal Agreement - Storm & Drainage Improvement - West of the South Forks Brays Bayou, UPIN 24104MF39201, Precinct 4.
end
Background and Discussion:
This project is part of the call for projects applications in 2023. It is a storm & drainage improvement project, West side of the South Fork Brays Bayou (D132-00-00), between Alief Clodine Road and Winkleman Road, more specifically just south of the pedestrian bridge which connects Magnolia Park and the Mission Bend Greenbelt Trails to Petrosky Elementary School. This project includes diverting water away from the trail and the adjacent ditch slope by directing flow to the back slope swales, demucking of overly silted and overgrown areas within the back slope swales, regrading of the back slope swale, installing a new drainage inlet, installing a new outfall culvert to the ditch, and re-grading the ditch slope.
Expected Impact:
This project will excavate and rebuild the ditch side slope. It will provide a fortified slope and eliminate the need for the County to eventually address any larger scale slope failures that would surface over time.
Alternative Options:
The alternative option for this proposal would be to deter...
Click here for full text