Title: Request for approval of a change in contract with MB Western Industrial Contracting Co., in connection with Bridge Repair - Brinsap 2020 Package 2 - 2022, adding 4 calendar days, with an addition in the amount of $11,398.00, Job No. 24/0052-3, UPIN 23103MF2P001, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0052, UPIN 23103MF2P001
Vendor/Entity Legal Name (if applicable): MB Western Industrial Contracting Co.

MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MB Western Industrial Contracting Co., in connection with Bridge Repair - Brinsap 2020 Package 2 - 2022, adding 4 calendar days, with an addition in the amount of $11,398.00, Job No. 24/0052-3, UPIN 23103MF2P001, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 100%.
end

Background and Discussion:
The Bridge Repair - Brinsap 2020 Package -2 project site consists of improvements and repair of bridges in various locations within Harris County. Major work activities include erosion repairs to seven bridges in Harris County - Precinct 3. Erosion repair work includes restoring eroded channel sections mainly below the bridge and a ditch, re-installing failed riprap, installing new riprap, replacing failed existing concrete slope paving, installing new concrete slope paving, backfilling undermined abutment caps, undermined bottom of box culverts and undermined concrete slope paving, replacing sections of corrugated metal pipes, and backfilling sinkholes.

The changes in contracts include:
* An additional quantity of 112.4 Square Yard of Sodding for the existing line item # 073 is needed to install as proposed in the p...