Department: County Engineer
Department Head: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Atascocita Complex Infrastructure Improvements
Project ID (if applicable): ATASCOCITA
Vendor Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Managing Entity: County Engineer
Incremental Authorization Requested: $13,310,000
Total Estimated Project Cost: $20,710,000
Request Summary:
title
Request for approval of a Final Investment Memo for the Atascocita Complex Infrastructure Improvements project, for an initial authorization of $13,310,000, and request approval of initial commercial paper funding in the amount of $8,350,000.[CB1]
end
Project Description:
The project includes design and construction of water, wastewater, and drainage improvements and repairs to critical facilities in the Atascocita Complex to further Harris County's resiliency initiative goals. The Atascocita Complex includes a Harris County Sheriff's Office Academy, Vehicle Barn, and firing range, a Harris County Public Health building, Harris County Fire Marshal facilities, Precinct facilities, Harris County Community Supervision & Corrections Department facilities, the Pam Lychner State Jail, and other facilities. The project includes the construction of a fire water loop to ensure all existing facilities and active projects on the site meet fire code, the design and construction of water lines to tie all facilities into the City of Houston water system, the design and construction of repairs to the sanitary sewer system, and the design and construction of drainage repairs. There is a potential to be reimbursed by the State for portions of the work. The County Attorney's Office is investigating...