File #: 26-7665    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 11/6/2026 In control: Commissioners Court
On agenda: 11/19/2026 Final action:
Title: Request for approval of a change in contract with Mar-Con Services, LLC, in connection with final construction of Miller Road 2 – Wallisville Road to US 90 - 2022, adding 267 calendar days, with an addition in the amount of $548,921.20, Job No. 23/0443-1, UPIN 22101MF2CW01, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 100%.
Attachments: 1. 26-7665-CIC-22101MF2CW01-Miller Rd 2-23-0443-1.Final-MarCon Svcs-P1-11192026.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0443, UPIN 22101MF2CW01
Vendor/Entity Legal Name (if applicable): Mar-Con Services, LLC

MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Mar-Con Services, LLC, in connection with final construction of Miller Road 2 – Wallisville Road to US 90 - 2022, adding 267 calendar days, with an addition in the amount of $548,921.20, Job No. 23/0443-1, UPIN 22101MF2CW01, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 100%.
end

Background and Discussion:
Harris County intends to provide improvements to Miller Road 2, from Wallisville Road to US 90. The pavement is planned to be re-constructed from asphalt to concrete pavement.

Change order includes the following items:
PCO - 4 RFI#024 - Electro Quip Cost Est - (RFI - 24) $28,932.22 zero calendar days
PCO - 6 RFI#029 - Guardrail Issues (at Kimberlee Street) - (RFI - 29) $2,884.70 2 calendar days
PCO - 8 RFI#032 - 5in Slope Paving - (RFI - 32) $5,827.00 15 calendar days
PCO - 9 Final - Miller Road 2 - Wallisville Road to US 90 - 2022 $509,822.68 zero calendar days
PCO - 5 RFI#028 - Concrete Barrier - (RFI - 28) $1,454.60 zero calendar days
PCO - 7 RFI#026 - Project Delays - (RFI - 26) $0.00 250 calendar days



Expected Impact:
The unobstructed visibility easement will allow us to move forward with the ...