Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0341, UPIN 24101MF3FT01
Vendor/Entity Legal Name (if applicable): Sago Solutions, LLC.
MWBE Contracted Goal (if applicable): 29.12%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sago Solutions, LLC, in connection with final construction of On-Call - Asphalt Repairs - 2024, with an addition in the amount of $23,396.83, Job No. 24/0341-1, UPIN 24101MF3FT01, Precinct 1, MWBE Contracted Goal: 29.12%, MWBE Current Participation: 100%.
end
Background and Discussion:
Project includes the maintenance of asphaltic concrete and general construction services throughout Precinct 1. Construction of these improvements performed by Sago Solutions, LCC ensures that the projects are built in accordance with the Harris County regulations. The change in contract is to add $23,396.83 to the contract amount with 0 calendar days. The change in contract is to include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. At the request of the Precinct this purchase order is being closed.
Expected Impact:
This project improves the condition and resilience of County transportation including park trails and general construction services at various locations throughout Precinct 1. Allow Contractor to be compensated for actual work orders that are completed within the Precinct 1...