Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Adrian Garcia, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 26289MF40101
Vendor/Entity Legal Name (if applicable): East Aldine Management District
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): Infrastructure (Design, Construction, Maintenance)
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with East Aldine Management District for providing leverage funding for a Community Development Block Grant Funded project, Sanitary Sewer System - Castledale Drive, UPIN 26289MF40101, Precinct 2.
end
Background and Discussion:
Request to execute an interlocal agreement between Harris County and the East Aldine Management District. The project has $640,710.00 in grant funding and the East Aldine Management District will provide $166,200.00 in leverage funding, totaling $806,910 budget for construction. This project consists of the construction of approximately 583-ft of 8-inch sanitary sewer line, sanitary sewer manholes, service connections, and septic system abandonments to eligible residents along Castledale Drive.
Expected Impact:
County will have leverage funds provided by East Aldine Management District to advertise this grant-funded
project.
Alternative Options:
County would be required to determine other resources to provide leverage funds for this project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-ma...