Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones.
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable):25104MF3S101
Vendor/Entity Legal Name (if applicable): Tomball Business Improvement District No. 1
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Tomball Business Improvement District No. 1 to construct widening and drainage improvements to Boudreaux Road, including a temporary traffic signal at Shaw Road in connection to Road Improvements - Boudreaux Rd - Shaw Rd to Rockey Rd - 2025 project, UPIN 25104MF3S101, Precincts 3 and 4.
end
Background and Discussion:
Boudreaux Rd from Shaw Rd to Rocky Rd will be constructed by a developer via a partnership agreement. Drainage facilities (open channel and detention pond) will be constructed for the detention and mitigation of the roadway. Maintenance of these facilities will need to be agreed upon before construction by the developer to have a seamless transition from construction phase to operation.
Expected Impact:
The drainage facilities will be maintained by the Tomball Business Improvement District No. 1 to construct roadway widening, which will allow for better traffic flow in the vicinity of the newly developed 240-acre tract.
Alternative Options:
Alternative options would be acquiring the property from the developer and providing maintenance with the precinct crews or a more costly drainage opt...