Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN - 25035MF3SB01
Vendor/Entity Legal Name (if applicable): Ally General Solutions, LLC
MWBE Contracted Goal (if applicable): 20.09%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Ally General Solutions, LLC in the amount of $88,661.50 for professional engineering services to provide a new traffic signal with pedestrian related appurtenances at the intersection of Cypresswood Drive at Cypress Mill Place Boulevard, UPIN 25035MF3SB01, Precinct 3, MWBE Contracted Goal: 20.09%.
end
Background and Discussion:
Traffic signals are constructed to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection and an evaluation of left turn storage to improve operations. The consultant will also be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.
Expected Impact:
Designing and building a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.
Alternative Options:
An alternative is to not build a signal at the intersection, which will not provide up to date operations and pedestrian benefits.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably ...
Click here for full text