Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: Not applicable
Regular or Supplemental RCA: Regular RCA
Type of Request: Public Necessity
Project ID (if applicable): 27101LOHWE01
Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder
MWBE Contracted Goal (if applicable): Not applicable
MWBE Current Participation (if applicable): Not applicable
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): Not applicable
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire, one (1) fee simple tract for the Tidwell Extension - BW8 to Pineland, for the purpose of roadway construction, UPIN 27101LOHWE01, Precinct 1.
end
Background and Discussion:
The purchase of the approximately 1.3-acre tract from the City of Houston to Harris County is essential to secure legal access and complete the right-of-way for Tidwell Road. It will establish a continuous right-of-way connection from Beltway 8 to Pineland Rd via Tidwell Road. This is a strategic portion of the Harris County thoroughfare plan.
Expected Impact:
This conveyance will establish a continuous right-of-way connection from Beltway 8 to Pineland Rd via Tidwell Road. Acceptance and recording would address an existing gap in the current right-of-way of Tidwell.
Alternative Options:
If Commissioners Court does not approve the proposed dedication, the right-of-way connection will remain unresolved, leaving Tidwell Road without the necessary legal access. The parties have evaluated all alternative rout...