Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Marcus Stuckett, P.E., CFM Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Asset Management
Project ID (if applicable): 24090MF3E301
Vendor/Entity Legal Name (if applicable): Not applicable
MWBE Contracted Goal (if applicable): Not applicable
MWBE Current Participation (if applicable): Not applicable
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): Not applicable
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval for County of Harris, a body corporate and politic under the laws of the State of Texas to convey real estate to Harris County Flood Control District, a political subdivision of the State of Texas, for tract K500-31-00-09-001.0, a 42.6536 acre Drainage and Detention Easement for Stormwater Detention for Cypress Creek Channel Rehabilitation - K500-31-00-E001 project and that the County Judge execute the Drainage and Detention Easement, UPIN 24090MF3E301, Precinct 3.
end
Background and Discussion:
Request for approval for Harris County to convey a drainage easement to HCFCD.
Expected Impact:
With the transfer of property, HCFCD will be able to construct the improvement(s) identified in this 2018 bond project.
Alternative Options:
The alternative to obtaining the required property rights is to not proceed with these segments of the project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
J...