Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: Not applicable
Regular or Supplemental RCA: Regular RCA
Type of Request: Public Necessity
Project ID (if applicable): 15104MF0DN03
Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder
MWBE Contracted Goal (if applicable): Not applicable
MWBE Current Participation (if applicable): Not applicable
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): Not applicable
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire, forty-one (41) road easement, twenty (20) temporary construction easement and sixteen (16) drainage easement tracts for the public project known as Telge Rd Segment 6 - from 300-ft North of Grant Rd to 690-ft North of SH99 - 2014, for the purpose of roadway construction, UPIN 15104MF0DN03, Precinct 3.
end
Background and Discussion:
The project involves the design and construction of the proposed expansion of Telge Rd Segment 6 - from 300-ft North of Grant Road to 690-ft North of SH99 to result in a four lane concrete boulevard. The project includes storm drain and sidewalks and detention basin mitigation and traffic signals.
Expected Impact:
The project will address current and future traffic volumes, reduce delays, and provide safe mobility for residents, pedestrians, and drivers.
Alternative Options:
If no action is taken, there will be delays in area mobility improvement.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distribut...