Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0216, UPIN 23103MF2TA01
Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC
MWBE Contracted Goal (if applicable): 36.09%
MWBE Current Participation (if applicable): 35.71%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners LLC, in connection with Treaschwig Rd A (Phase 2) - from west of Cypress Creek to 1,000' east of Birnam Wood Blvd - 2014, adding 5 calendar days, with an addition in the amount of $122,144.38, Job No. 25/0216-3, UPIN 23103MF2TA01, Precinct 3, MWBE Contracted Goal: 36.09%, MWBE Current Participation: 35.71%.
end
Background and Discussion:
This project consists of the reconstruction and widening of Treaschwig Road (Phase 2) from west of Whittaker Way to East of Birnam Wood Boulevard. The scope includes drainage improvements, construction of a new bridge over the creek, traffic signal installation, striping, and all other miscellaneous safety enhancements required.
This change in contract includes:
(PCO #8, RFI #6) Due to field conflicts, the 48-inch CMP had to be relocated to an area not originally designated for tree clearing and grubbing. The resulting additional tree-removal costs were reviewed and accepted by the Engineer of Record (EOR), Office of the County Engineer (OCE), and Precinct 3.
(PCO #9, RFI #29) Per Precinct request and proposal approval, CMP pipe North of the bridge will be extended to a...
Click here for full text