Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0352, UPIN 15104M23NP03
Vendor/Entity Legal Name (if applicable): Hassell Construction Group, LLC
MWBE Contracted Goal (if applicable): 33.31%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Hassell Construction Group, LLC in connection with Hufsmith-Kohrville Rd 3, with an addition in the amount of $14,744.13, Job No. 25/0352-1, UPIN 15104M23NP03, Precinct 3, MWBE Contracted Goal: 33.31%.
end
Background and Discussion:
The project section of road reconstruction and drainage improvements of Hufsmith-Kohrville Road - Segment 3A from North of Ezekiel Road to North of Boudreaux Road. This change in contract allows contractor to install temporary wood poles to provide the necessary support for the temporary traffic signal equipment while the permanent traffic signal poles are being procured, fabricated, and delivered, thereby maintaining the project schedule and ensuring a safe and fully functional temporary traffic signal operation.
The change in contract includes the following:
Temporary Poles Installation and Removal $ 14,744.13
Expected Impact:
This change will allow the Contractor to be properly compensated for the additional work.
Alternative Options:
Conduct thorough pre-construction assessments and detailed utility mapping to identify and mitigate potential conflicts early.
County Strategic Plan Goal: 2. Co...