Legislation Details

File #: 26-5796    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/1/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with Precise Services Inc., in connection with final construction of Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, with an addition in the amount of $198,593.10, Job No. 24/0408-2, Mobility Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0408, UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): Precise Services Inc.

MWBE Contracted Goal (if applicable): 22.81%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services Inc., in connection with final construction of Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, with an addition in the amount of $198,593.10, Job No. 24/0408-2, Mobility Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
end

Background and Discussion:
This project entails the construction of storm sewer drainage to convey drainage in the Cedar Bayou Park East
and West Subdivision from Sjolander Road to Bayou Boulevard.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

The increase of quantities on overrun line items 02, 03, 04, 12, 68, 76, 83, and 88 for an addition in the amount of $292,888.10.

The decrease of quantities on underrun line items 31, 41, 84, 93, 100, and 106 for a deduction in the amount of $94,295.00.

The above and additions and deductions result in an addition in the amount of $198,593.10 and zero (0) days.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris Co...

Click here for full text