Title: Request for approval of the Final Investment Memo for the Precinct 2 Aldine Gardens Camp IT System Infrastructure Upgrade project for an incremental amount of $100,000 for a total authorization of $378,092 and request for approval of commercial paper funding in the amount of $100,000 for a total amount of $380,000.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Commissioner, Precinct 2
Primary Department Head/Elected Official: Commissioner Adrian Garcia

Managing Department: Commissioner, Precinct 2
Managing Department Head/Elected Official: Commissioner Adrian Garcia

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Precinct 2 Aldine Gardens Camp IT System Infrastructure Upgrade
Project ID (if applicable): 100001000001824

Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $100,000
Total Estimated Project Cost: $378,092

Request Summary:
title
Request for approval of the Final Investment Memo for the Precinct 2 Aldine Gardens Camp IT System Infrastructure Upgrade project for an incremental amount of $100,000 for a total authorization of $378,092 and request for approval of commercial paper funding in the amount of $100,000 for a total amount of $380,000.
end

Project Description:
The additional funds requested are for the essential IT systems infrastructure installation within the Aldine Gardens Camp Facility managed by Precinct 2 and owned by Harris County. The objective of this project is to develop and implement the essential infrastructure for information technology, fire safety, security, and access control systems. This foundational framework will provide the necessary support for all future operational requirements.

Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Estimated Cost
Estimated Start/Completion

IT Systems Infrastructure Upgrades (Additional Funds being requested for construction/installation).
$ 126,793
FY2027

Funds Available from Contin...

Click here for full text