File #: 25-4380    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/1/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a change in contract with Solid Bridge Construction, LLC, in connection with final construction of Detention Basin Enhancement Program - Cypress - 2021, with a deduction in the amount of $22,636.04, Job No. 23/0463-2, UPIN 21103N306430001, Precinct 3, MWBE Contracted Goal: 24%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0463, UPIN 21103N306430001
Vendor/Entity Legal Name (if applicable): Solid Bridge Construction, LLC

MWBE Contracted Goal (if applicable): 24%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Solid Bridge Construction, LLC, in connection with final construction of Detention Basin Enhancement Program - Cypress - 2021, with a deduction in the amount of $22,636.04, Job No. 23/0463-2, UPIN 21103N306430001, Precinct 3, MWBE Contracted Goal: 24%.
end

Background and Discussion:
The (K500-01-00 Detention Basin Expansion) project site consists of stormwater detention basin located northwest of Harris County in Cypress Creek Watershed, discharging into Harris County Flood Control Channel K100-01-00 Cypress Creek. Its goal is to provide a stormwater quality detention pond, achieving the full intended functionality of the basin to enhance drainage and reduce flooding risks. The project was overseen by the Office of County Engineer.

This final change order is for a deduction of the final adjustment in the amount of $22,636.04.
Final Adjustment is the reconciliation of actual quantities used in construction against the bid quantities.
Added Items:

PCO #2 Supports Under Valve: $13,189.50 0 Days
PCO #3 Final Adjustment: ($22,636.04) 0 Days ...

Click here for full text