Legislation Details

File #: 26-5988    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/3/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with MC2 Civil LLC, in connection with final construction of Bridge Maintenance - De Zavalla Road at HCFCD Unit N101-00-00 - 2024, with an addition in the amount of $38,978.84, Job No. 25/0404-1, UPIN 24102MF3AH01, Precinct 2, MWBE Contracted Goal: 27.80%, MWBE Current Participation: 25.21%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0404, UPIN 24102MF3AH01
Vendor/Entity Legal Name (if applicable): MC2 Civil LLC

MWBE Contracted Goal (if applicable): 27.80%
MWBE Current Participation (if applicable): 25.21%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
...title
Request for approval of a change in contract with MC2 Civil LLC, in connection with final construction of Bridge Maintenance - De Zavalla Road at HCFCD Unit N101-00-00 - 2024, with an addition in the amount of $38,978.84, Job No. 25/0404-1, UPIN 24102MF3AH01, Precinct 2, MWBE Contracted Goal: 27.80%, MWBE Current Participation: 25.21%.
...end

Background and Discussion:
The project includes erosion repairs along De Zavalla Road at HCFCD Unit N101-00-00 in Precinct 2. The work includes extending the existing steel sheet pile wall, removing and replacing the failed asphalt shoulder, repairing/extending the existing guardrail and mowing strip, and installing riprap
This change in contract includes:

PCO#1 – This change order is required to address unforeseen field conditions and operational constraints encountered during construction of the De Zavalla Bridge project. To maintain safe access for the traveling public and adjacent businesses during construction work, the Contractor must implement additional traffic control measures, including police officers and/or flaggers, portable light towers, and additional labor to open and close the roadway each workday. Nighttime operations are also necessary to...

Click here for full text