File #: 26-5957    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/3/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Houmont Park Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $16,063.25, Job No. 25/0194-3, HC Road Fund, UPIN 19101MF14G01, Precinct 1, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 56.54%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0194, UPIN 19101MF14G01
Vendor/Entity Legal Name (if applicable): SER Construction Partners LLC

MWBE Contracted Goal (if applicable): 32.17%
MWBE Current Participation (if applicable): 56.54%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Houmont Park Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $16,063.25, Job No. 25/0194-3, HC Road Fund, UPIN 19101MF14G01, Precinct 1, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 56.54%.
end

Background and Discussion:
The Houmont Park Subdivision Drainage Improvements - HCFCD Unit No. P110-04-00 & P110-00-00 project site consists of subdivision drainage and roadway improvements located between C E King Parkway and Van Hut Lane. The project includes roadside ditch improvements along Unison Rd and Ticonderoga Rd and channel improvements on P110-04-00 and P110-00-00. Two detention basins will be excavated to mitigate for the conveyance improvements for this project.

The change in contract includes the following:

The line items are adjusted to reconcile overrun quantities and add new line items to the project for completion of the proposed scope of work.

The increase in quantities on overrun line item number 121 for an addition in the amount of $13,740.25 and zero (0) days.

Added new line item needed to complete the ...

Click here for full text