File #: 24-7590    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/26/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of change in contract No. 3 with Allgood Construction Company, Inc., for the excavation of Inwood Forest Stormwater Detention Basin (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWDBE Contracted Goal: 37%, MWDBE Current Participation: 44.68%).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): E500-21-00-E002
Vendor/Entity Legal Name (if applicable): Allgood Construction Company, Inc.

MWDBE Contracted Goal (if applicable): 37%
MWDBE Current Participation (if applicable): 44.68%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Allgood Construction Company, Inc., for the excavation of Inwood Forest Stormwater Detention Basin (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWDBE Contracted Goal: 37%, MWDBE Current Participation: 44.68%).
end

Background and Discussion:
This project is a collaborative effort between the Flood Control District and the City of Houston to construct 12 interconnected stormwater detention basins on the former Inwood Forest Golf Course property. This Contract Change includes increases in quantities for various items, changes to preserve trees, and partner requests. This will be a $0 contract change as the additional costs will be offset through reductions in other items that are no longer needed.

Expected Impact:
This change will allow the contractor to construct the project so that the area can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
...

Click here for full text