Legislation Details

File #: 26-5499    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 8/12/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval to execute an agreement with DECON, LLC. in the amount of $1,199,707.00 for Professional Engineering Services in connection with Precinct One Infrastructure Revitalization Program - Group A, UPIN 26101HKE7B01, Precinct 1, MWBE Contracted Goal: 19.00%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 26101HKE7B01
Vendor/Entity Legal Name (if applicable): DECON, LLC.

MWBE Contracted Goal (if applicable): 19.00%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with DECON, LLC. in the amount of $1,199,707.00 for Professional Engineering Services in connection with Precinct One Infrastructure Revitalization Program - Group A, UPIN 26101HKE7B01, Precinct 1, MWBE Contracted Goal: 19.00%.
end

Background and Discussion:
Design and construction of pavement rehabilitation development and construction for the 2026 Precinct 1 Pavement Rehabilitation Packages Group A Packages 2, 7, 8 (~10.3 miles).

Expected Impact:
This action will allow DECON, LLC. to provide professional engineering services for the project.

Alternative Options:
No alternative options. If not approved, project will be delayed or cancelled.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
...