Legislation Details

File #: 26-6537    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 9/29/2026 In control: Commissioners Court
On agenda: 10/15/2026 Final action:
Title: Request for approval of an award on the basis of low bid to Queen Constructors LLC in the amount of $2,947,084 for construction of hike and bike trails along CE King Parkway from Tidwell Road to Garrett Road for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (260257), MWBE Contracted Goal: 32.12%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable):260257
Vendor/Entity Legal Name (if applicable): Queen Constructors LLC

MWBE Contracted Goal (if applicable): 32.12%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Queen Constructors LLC in the amount of $2,947,084 for construction of hike and bike trails along CE King Parkway from Tidwell Road to Garrett Road for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (260257), MWBE Contracted Goal: 32.12%.
end

Background and Discussion:
The project is to construct approximately 2.2 miles of 12-foot wide, 6-in thick concrete bike trail along east side of CE King Parkway from Tidwell Road to Garrett Road. The project also includes a three-span pedestrian bridge at HCFCD Channel P121-00-00.

Expected Impact:
The project will provide safe pedestrian and bike routes along CE King Parkway.

Alternative Options:
No alternative options available. The construction will be delayed or cancelled.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County’s commitment to Vision Zero principles and goa...

Click here for full text