Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Asset Management
Project ID (if applicable): P130-02-00-X017
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a new unit designated as P530-02-02 to be accepted as part of the Flood Control District's maintenance system (Greens Bayou Watershed, Project ID P130-02-00-X017, Precinct 3).
end
Background and Discussion:
This request is to document the acceptance of the development basin P530-02-02, which was originally constructed to serve the adjacent Harris County MUD No. 23 neighborhood. In addition to its intended drainage function, this basin provides critical access to the P130-02-00 channel, which is otherwise surrounded by heavily wooded and undeveloped properties, thereby limiting entry for Flood Control District maintenance and mowing operations.
As part of Flood Control District Maintenance Project P130-02-00-X017, the basin was utilized as an access point to complete portions of the project. This access was granted through an agreement with Harris County MUD No. 23, under which Flood Control District committed to accepting the basin for ongoing maintenance in exchange for use of the property for project access.
Harris County MUD No. 23 recently repaired the basin to bring it to Flood Control District acceptability standards. The Flood Control District Development Coordination and Inspection Department (DCID) monitored t...
Click here for full text