File #: 25-4698    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/23/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval to reduce retainage by 2% (from 5% to 3%) on Contract 350 for Traffic Systems Construction, Inc. for improvements to the Sam Houston Tollway between US-59 South and US-290, consisting of the installation of High-Mast Illumination (Precincts 3 and 4).
Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Contract 350
Vendor/Entity Legal Name (if applicable): Traffic Systems Construction, Inc.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to reduce retainage by 2% (from 5% to 3%) on Contract 350 for Traffic Systems Construction, Inc. for improvements to the Sam Houston Tollway between US-59 South and US-290, consisting of the installation of High-Mast Illumination (Precincts 3 and 4).
end

Background and Discussion:
Contract No. 350 is the replacement of 178 existing barrier-mounted light fixtures on Sam Houston Tollway, between US-59 South and US-290 with 78 LED high mast light fixtures, along with the replacement of electrical services throughout this corridor. The project is substantially complete, with only some existing electrical services which need to be disconnected by CenterPoint-Electric. As such, the contractor has requested and HCTRA concurs, that the retainage on the project be reduced. The release of 2% of the overall retainage will still allow for coverage any expenses identified as part of the final project closeout.

Expected Impact:
No additional funding is required as the project is substantially complete. The payment of the released retainage will come from the Toll Road Authority approved funding for the project.

Alternative Options:
No other recommended solutions. Should this r...