File #: 26-5455    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/11/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of a change in contract with McCrory - CTI Services Inc., in connection with final construction of Dula Lane and Related Infrastructure Drainage Improvements Project, adding 51 calendar days, with an addition in the amount of $203,458.80, Job No. 24/0144-2, UPIN 22208MF2H701, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 30.57%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E.

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0144, UPIN 22208MF2H701
Vendor/Entity Legal Name (if applicable): McCrory - CTI Services Inc.

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 30.57%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McCrory - CTI Services Inc., in connection with final construction of Dula Lane and Related Infrastructure Drainage Improvements Project, adding 51 calendar days, with an addition in the amount of $203,458.80, Job No. 24/0144-2, UPIN 22208MF2H701, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 30.57%.
end

Background and Discussion:
This project includes the installation of approximately 2,000 Linear feet of underground drainage utilities, and
the reconstruction of asphalt pavement, driveway, and regrading of the roadside ditch throughout Dula Lane.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

* The increase in quantities on overrun line-item numbers 6, 8, 10, 12, 17, 18, 24, 25, 27, 37, 42, 45, 51, 62 and 63 for an addition in the amount of $214,387.10
* The decrease of quantities on underrun line-item numbers 3A, 15, 16, 19, 22, 26, 28, 29, 32, 38, 46, 47, 48, 52, 53, 55, 57, 58, 59, 61 and 100 for a deduction in the amount of $83,916.08.

New...