File #: 24-1548    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/14/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of a change in contract with Brice Construction & Design, LLC, in connection with Mueschke 8; 2,700' South of Draper Road to approximately 500' North of Draper Road, adding eight calendar days, with an addition in the amount of $163,112.04, Job No. 23/0230-1, UPIN 161033020711, Precinct 4, MWDBE Contracted Goal: 27.56%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 23/0230, UPIN 161033020711
Vendor/Entity Legal Name (if applicable): Brice Construction & Design, LLC

MWDBE Contracted Goal (if applicable): 27.56%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Brice Construction & Design, LLC, in connection with Mueschke 8; 2,700' South of Draper Road to approximately 500' North of Draper Road, adding eight calendar days, with an addition in the amount of $163,112.04, Job No. 23/0230-1, UPIN 161033020711, Precinct 4, MWDBE Contracted Goal: 27.56%.
end

Background and Discussion:
The temporary construction detour was designed by the Engineer of Record and installed per the plans. After installation several spots of the detour began to degrade, and the road began to fall apart. Precinct 4 received numerous complaints and advised that they wanted the detour rebuilt to withstand the traffic the road handles daily. After consulting with the Engineer, it was determined that the soils on site were insufficient to hold up to road standards. The engineer recommended removing the unsuitable soils and replacing them with select fill. Also, the recommendation was made to thicken the base layer to double what was designed originally. The additional work was approved by Precinct 4.

* Changes associated with the additional work include Removing existing Asphalt Base, Borrow Fill, Special Excavation, Additional Detour installations, and additional Uniformed Off Duty Police Hours for Traffic Control.

Expected Impact:
The temporary detour once reconstructed should allow for vehicles to safely travel the roadway during our c...

Click here for full text