Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): T100-00-00-X002
Vendor/Entity Legal Name (if applicable): Cobb, Fendley & Associates, Inc.
MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Cobb, Fendley & Associates, Inc., in the amount of $908,092.74, to provide engineering, design, bidding and construction phase engineering services in support of major maintenance activities to restore channel conveyance capacity in Barker Reservoir watershed. (Barker Reservoir Watershed, Bond ID C-53, Project ID T100-00-00-X002, Agreement No. 2022-196, Precinct 4, MWDBE Contracted Goal: 20%).
end
Background and Discussion:
As a part of the Flood Control District’s maintenance operations, the Flood Control District undertakes multiple projects to de-silt channels on a routine basis. The Flood Control District has a need for additional sediment removal projects and bank repairs within the Barker Reservoir to assure proper drainage into the reservoir. This project will improve storm water conveyance by restoring several channels within Barker Reservoir to the original capacity to hold and convey storm water. The project consists of the removal of sediment from various tributaries within Barker Reservoir and repairs along the banks where needed so that flows will not be interrupted. This project does not have a score using the 2022 Prioritization Framework because it is a channel maintenance project.
Expected Impact:
This item will authorize the prime consultant to begin engineering designs for removal of sediment in the channels and repair deficiencies noted within them. The Flood Control District staff will manage the engineering consultant team to execute the engineering designs for this project.
Alternative Options:
There is not an alternative option other than not performing the project. Not maintaining the channels within the reservoir will increase the probability of flooding to the residents upstream of the reservoir as water flow would into the reservoir would be restricted.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
10/25/2022 |
88. |
ATN |
Location: N/A
Address (if applicable):
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
4.a.3 - Engineering Services |
|
FY 24 |
FY 25 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$908,092.74 |
$ |
$ |
Total Incremental Expenditures |
$908,092.74 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Bonds |
$908,092.74 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$908,092.74 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$908,092.74 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: November 14, 2023
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Agreement and map