File #: 24-5989    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 9/11/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request by the District Clerk for approval of a Final Investment Memo for the District Clerk Restroom Addition project for an initial amount of $284,500.

Department: District Clerk

Department Head: Marilyn Burgess

 

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: District Clerk Restroom Addition

Project ID (if applicable): TBD

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: Office of County Engineer

Incremental Authorization Requested: $284,500                                                                                                                                                   

Total Estimated Project Cost: $284,500

 

Request Summary:

title

Request by the District Clerk for approval of a Final Investment Memo for the District Clerk Restroom Addition project for an initial amount of $284,500.

end

 

Project Description:

The District Clerk’s Office (DCO) is requesting the renovation of the 1st floor restrooms at 5900 Canal to address critical deficiencies in the existing facilities. The proposed renovation will introduce modern, efficient restrooms designed to accommodate the current and anticipated increase in staff levels. As the number of employees and officers at the facility continues to grow, these upgraded restrooms will ensure that all personnel have access to adequate and sanitary facilities, significantly enhancing comfort and operational efficiency.

 

Project Scope:

The detailed scope of work for the 1st floor restroom renovation at 5900 Canal is listed in the table below. The proposed costs of this project include a $6,300 consultant fee from Gordian. In addition, a $26,000 contingency cost for unforeseen issues is included for a total of $284,500. Please see an overview of the scope of work below:

                     Site Preparation: Includes site clearing, grading, and excavation as necessary for the renovation.

                     Structural Work: Encompasses concrete removal and replacement, masonry work for new walls and partitions, and repair of existing structural elements.

                     Finishes and Installations: Involves applying durable finishes to walls, floors, and ceilings; installing restroom fixtures, partitions, and accessories; and ensuring seamless integration into the existing design.

                     Systems Upgrades: Covers the upgrade of plumbing systems, installation of new HVAC systems for proper ventilation, and updating electrical systems to support new fixtures and lighting.

                     Protection Measures: Includes installation of moisture-resistant materials and thermal insulation to ensure durability and comfort.

While minor operational adjustments may occur during this project, the overall scope of the restroom renovation project will remain consistent. Any significant changes or additional authorizations will require approval from the Commissioners Court.

 

Justification:

The renovation of the 1st floor restrooms at 5900 Canal is essential due to the current inadequacies in restroom facilities, which are unable to support the growing number of staff and officers using the building. The existing facilities are frequently overcrowded, leading to discomfort and potential disruptions in work efficiency.

Upgrading to modern, efficient restrooms will enhance staff comfort and improve operational efficiency. This project will address these critical issues, providing a functional and sanitary environment that supports the increased demand and maintains high standards of workplace functionality.

 

Alternatives and Engagement:

Not funding this project would continue to exacerbate the existing congestion, leading to diminished staff comfort and potential disruptions in work efficiency at the location. Additionally, delays in this project may increase costs due to increased costs of material and labor.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

Estimated Cost

Estimated Completion

General Requirements

$55,300

 

Site Work

$4,000

 

Concrete

$15,100

 

Masonry

$15,800

 

Thermal and Moisture Protection

$2,500

 

Openings

$13,000

 

Finishes

$97,500

 

Specialties

$13,400

 

Upgrade Plumbing System

$24,700

 

Install New Electrical System

$9,100

 

Earthwork

$1,800

 

Gordian (Consultant)

$6,300

 

Contingency (10%)

$26,000

 

Total

$284,500

-

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Previous Court Action: N/A

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

 

Address: 5900 Canal St, Houston, Texas, 77011

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19, 2024

Anticipated Implementation Date (if different from Court date): N/A

Legal funding compliance confirmed by: Paige Abernathy, CAO, 9/9/2024

Department Approval by: Wes McCoy, Chief Deputy of Administration

OMB CIP Team Approval by: Amiel Chen, OMB, CIP Manager, 9/3/24

 

 