Legislation Details

File #: 25-0389    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 12/30/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a Final Investment Memo for the Energy Infrastructure Pilot, installing Distributed Energy Resources (DERS) at Community Centers and Libraries in Harris County for an additional authorization of $9,938,530 for a total authorization of $10,138,530 and commercial paper funding for an additional $3,500,000 for a total allocation of $3,700,000.

Primary Department: County Administration

Primary Department Head/Elected Official: Diana Ramirez, County Administrator

Managing Department: County Engineer

Managing Department Head/Elected Official: Milton Rahman

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Energy Infrastructure Pilot, Installation of Distributed Energy Resources at Community Centers and Libraries in Harris County

Project ID (if applicable): SOLARSTORAGE

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): 15%

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Incremental Authorization Requested: $9,938,530

Total Estimated Project Cost: $10,138,530

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Energy Infrastructure Pilot, installing Distributed Energy Resources (DERS) at Community Centers and Libraries in Harris County for an additional authorization of $9,938,530 for a total authorization of $10,138,530 and commercial paper funding for an additional $3,500,000 for a total allocation of $3,700,000.

end

 

 

 

Project Description:

In October of 2022, the Commissioner’s Court approved a preliminary investment memo for Harris County’s Distributed Energy Resources (DERS) pilot. This project has been designed to invest in select libraries and community centers with distributed energy technology such as solar panels and battery storage, to make these locations more resilient to extreme weather and events impacting the power grid. The goal was to understand how to achieve a level of scale to install this technology in County facilities. The package for each site includes solar panels, battery storage, and level 2 dual-port electric vehicle charging stations. In addition to increasing resiliency, this project will allow the County to be less reliant on the electricity grid, reduce energy usage, and increase load flexibility.

The 16 sites identified for this project will be implemented in two phases. The first eight locations will be completed over the 12 months beginning January 2025 with all eight to be completed by Q1 of 2026. The final eight sites will be subject to additional evaluation and design over the course of 2025.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

PHASE I - FINAL DESIGN & CONSTRUCTION

 

 

Lincoln Park Community Center

$376,659.34

Q1 CY2026

Finnigan Community Center

$672,321.96

Q1 CY2026

Bay Area Community Center

$414,161.08

Q1 CY2026

Almendarez Community Center

$608,879.90

Q1 CY2026

Trini Mendenhall Community Center

$583,136.74

Q1 CY2026

George Bush Community Center

$542,206.96

Q1 CY2026

Steve Radack Community Center

$912,485.10

Q1 CY2026

Bayland Community Center

$471,683.04

Q1 CY2026

PHASE II

 

 

Adair Community Center

$346,077.28

Q1 CY2027

Health Care Annex Cavalcade Community Center

$214,407.26

Q1 CY2027

Challenger Seven Center/Park

$708,550.64

Q1 CY2027

Aldine Branch Library

$694,556.52

Q1 CY2027

Baldwin Boettcher Branch Library

$364,002.94

Q1 CY2027

Barrett Station Community Center

$986,979.78

Q1 CY2027

Weekley Community Center

$527,760.22

Q1 CY2027

 [Katy Branch Library]

$611,158.37

Q1 CY2027

Contingency (10%)

$903,502.71

Q1 CY2027

Total

$9,938,529.84

 Q1 CY2027

 

Justification & Alternatives:

The preliminary investment memo projected three sites per-precinct and significantly smaller solar and battery arrays. Through further investigation of sites identified by precinct staff, larger systems were needed to cover the building’s energy usage and all of the sites that were investigated were good candidates for the project. The project originally conceived of 100 kW solar systems on every site, with the final bids averaging 321 kW systems per site.

The increase in equipment per site, as well as outfitting 16 sites instead of 12, caused an increase in the projected cost of the project. Overall, ~2/3 of the cost increase is attributable to the increase in project site, with ~1/4 attributable to cost increases in equipment and labor beyond the 2022 projections.

Despite the cost increases, these investments provide a positive financial benefit to the County. A benefits-cost analysis was performed for the PIM with projected costs as well as with the final costs. While the cost increases represented a decrease in the IRR, the current project provides a strong return on investment. We currently project a 9.5% IRR to the County with a simple payback of nine years. These returns come from the solar-generated, the value of energy storage, as well as some resilience benefits of each site.

In addition, there are a number of additional financial benefits not considered in our analysis. The benefit-cost analysis below does not consider the sale of Renewable Energy Credits, contribution to a County demand response program, or any financial value to the avoided cost of carbon.

 

 

 

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  Choose an item.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): R1: Embed resiliency hubs within vulnerable communities to increase access to emergency resources.

Housing Initiative (Goal 6): Choose an item.

 

Previous Court Action:

Date

Agenda Item #

Action Taken

2/8/2022

270

Transmittal by OCA of Tradition Energy’s Clean Energy Strategy report

10/25/2022

17

Request for approval of a Preliminary Investment Memo for the Energy Infrastructure Pilot program for an initial authorization of $200,000.

9/19/2024

321

Approval of an award to METCO ENGINEERING, INC. for installation of distributed energy resources at Precinct 2 & 3 community centers and libraries.

 

Address:

Precinct(s): Choose an item.

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$3,500,000

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$3,500,000

$

$

Total Funding Request

$

$3,500,000

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Legal funding compliance confirmed by:

Department Approval by: Jesse Dickerman, Managing Director, OCA,12/23/2024

OMB CIP Team Approval by:

 

Commercial Paper Request (For OMB use only):

Receiving Department: County Engineer

Project PeopleSoft ID: SOLARSTORAGE

CP Series Description: Commercial Paper Series D can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Energy Infrastructure Pilot project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

 

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget