Legislation Details

File #: 25-1457    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/5/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval to execute an agreement with Gauge Engineering LLC., in the amount of $160,000.00 for Construction Phase Services in connection with Wortham Estates Subdivision Drainage Improvements - 2018, UPIN 19103MF15701, Precinct 3, MWBE Contracted Goal: 20%, MWBE Current Participation: 25.8%.
Attachments: 1. Award-UPIN 1903MF15701-CPS-Wortham Estates-Gauge-P3-v05.pdf

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 19103MF15701

Vendor/Entity Legal Name (if applicable): Gauge Engineering LLC.

 

MWBE Contracted Goal (if applicable): 20%

MWBE Current Participation (if applicable): 25.8 %

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Gauge Engineering LLC., in the amount of $160,000.00 for Construction Phase Services in connection with Wortham Estates Subdivision Drainage Improvements - 2018, UPIN 19103MF15701, Precinct 3, MWBE Contracted Goal: 20%, MWBE Current Participation: 25.8%.

end

 

Background and Discussion:

This project is located at Huffmeister Road and Fallbrook Drive, Houston, TX 77065. The project drains into HCFCD Unit No. E133-00-00. The scope and proposed improvements include providing stormwater detention storage to reduce flooding for subdivisions which drain into E133-00-00 and E133-01-00. It will also serve to mitigate two future drainage improvement projects: (1) within the Barwood Subdivision that ultimately outfalls into E133-00-00 and (2) the future Fallbrook Drive extension to Huffmeister Road to the existing Fallbrook Drive located at the eastern ROW of HCFCD Unit E133-00-00.

Expected Impact:

The project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Wortham Estates Subdivision.

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the project may not be constructed as scoped.

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H1: Complete and implement the Flood Resilience Plan.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/19/2022

22-4282

Authorization to Negotiate for Engineering Service

1/15/2022

22-7221

Contract Award for Professional Engineering Services

06/25/2024

24-3747

Contract Amendment for Professional Engineering Services

 

Location: Wortham Estates Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other (Precinct 3)

$

$160,000.00

$160,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$160,000.00

$160,000.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$160,000.00

$160,000.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/27/2025

Anticipated Implementation Date (if different from Court date): N/A Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure,

Office of the County Engineer

 

Attachments (if applicable): Professional Service Agreement