Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 22103N306630001
Vendor/Entity Legal Name (if applicable): Sander Engineering Corporation
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Sander Engineering Corporation for North Eldridge Parkway - from South of Pine Drive to South of Lakewood Meadow Drive - 2021, UPIN 22103N306630001, Precinct 3.
end
Background and Discussion:
The County engaged with Sander Engineering Corporation and initiated a professional services agreement in
January 2022, and amended the contract with Sander Engineering Corporation on June 2023 to facilitate the study and design changes associated with expanding the project scope requested by the County. The Study Report is to establish the existing conditions, analyze the impacts of improvements while considering feasible alternatives, and present recommendations. The Project roadway improvement limits are from south of Pine Drive to south of Lakewood Meadow Drive, and drainage improvement limits are from south of Pine Drive to Cypress Park detention pond.
Expected Impact:
Proposed improvements to North Eldridge Parkway include expanding the existing half of the boulevard to complete a full standard four lane concrete boulevard with curbing, storm sewers, curbed median, removal of existing asphalt transitions and left turn lanes.
Alternative Options:
If not approved, consultant will not be able to proceed with Design Phase tasks and may lead to project delays.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
September 14, 2021 |
135. |
Recommendation for authorization to negotiated with Sander Engineering Corporation |
|
January 25, 2022 |
44. |
Recommendation that the County Judge execute a professional services agreement with Sander Engineering Corporation |
|
June 6, 2023 |
40 |
Amend the Agreement to increase the limit of appropriations from a maximum appropriation of $470,254.73 to $704,864.52 to fund the additional work |
Location:
Address (if applicable): North Eldridge Parkway - from South of Pine Drive to South of Lakewood Meadow Drive - 2021
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: May 7th, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Study Report