Title: Request for approval to utilize a CMAR (Construction Manager-at-Risk) delivery method for the Tracy Gee Community Center Renovation project, and the Purchasing Agent be authorized to issue a Request for Qualifications (RFQ) and administer the selection of the Construction Manager based on reputation and quality. Once selected, the CMAR would assist the Architect of Record with constructability, value engineering, and cost estimates, and all phases of work under the CMAR will be publicly bid and the bidding process will be overseen by the Purchasing Agent and their office, UPIN 24104MF3BB01, Precinct 4.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Asset Management

 

Project ID (if applicable): UPIN 24104MF3BB01

Vendor/Entity Legal Name (if applicable): TBD

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to utilize a CMAR (Construction Manager-at-Risk) delivery method for the Tracy Gee Community Center Renovation project, and the Purchasing Agent be authorized to issue a Request for Qualifications (RFQ) and administer the selection of the Construction Manager based on reputation and quality. Once selected, the CMAR would assist the Architect of Record with constructability, value engineering, and cost estimates, and all phases of work under the CMAR will be publicly bid and the bidding process will be overseen by the Purchasing Agent and their office, UPIN 24104MF3BB01, Precinct 4.

end

 

Background and Discussion:

On July 15, 2024, Commissioners Court approved authorization to initiate the pre-design activities of the Tracy Gee Community Center, located at 3599 Westcenter Drive in Precinct 4. An RFQ process will be completed to select and award project for architectural and engineering services. The major renovations to the existing facility will consist of sustainable upgrades and additions with possible replacement as necessary to accommodate the growing needs of the community in Precinct 4.

 

Expected Impact:

Advertisement of the CMAR will allow the County to have a General Contractor under contract to work with the County during the design phases to help encumber funds in a timely manner for long-lead items. Procuring the General Contractor during design phase will also help manage the budget and schedule for the project.

 

Alternative Options:

Commissioner court could postpone the approval to utilize CMAR, however this will postpone the procurement of a General Contractor thus delaying the possibility to encumber funds in a timely manner and delay critical path schedule to encumber construction funds prior to end of Fiscal Year 2025.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/26/2024

141

Request for approval to negotiate with STOA International Architects, Inc. to provide professional engineering and architectural services

07/15/2024

302

Request for approval of Preliminary Investment Memo for the Tracy Gee Community Center Renovation project

07/15/2024

42

Request for approval to execute an agreement with STOA International Architects, Inc. to provide architecture and engineering services for pre-design phase of Tracy Gee Community Center project.

 

Location:

Address (if applicable): 3599 Westcenter Dr. Houston, TX 77042

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Ross Hosket, P.E., CFM, Env SP, Interim Director of Capital Project Facility

Division, Harris County Engineering Department

 

Attachments (if applicable): N/A