Legislation Details

File #: 25-2924    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 4/28/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval of the Change Investment Memo for the multiple projects to reconcile Precinct 3 FY 24-25 Facilities with no additional incremental authorization.

Primary Department: Commissioner, Precinct 3

Primary Department Head/Elected Official: Commissioner Tom S. Ramsey, P.E.

Managing Department: Commissioner, Precinct 3

Managing Department Head/Elected Official: Commissioner Tom S. Ramsey, P.E.

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Change Investment Memo

 

Project Name: Precinct 3 FY 24-25 Facilities Reconciliation

Project ID (if applicable): N/A

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $0

Total Estimated Project Cost: $0

 

Request Summary:

title

Request for approval of the Change Investment Memo for the multiple projects to reconcile Precinct 3 FY 24-25 Facilities with no additional incremental authorization.

end

 

Project Description:

N/A

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

 

 

 

Total

-

-

 

Justification & Alternatives:

Precinct 3 has received authorization in FY24 and FY25 to use commercial paper for a total of $15,000,000 for facility improvements as per OMB’s non-voted commercial paper policy. The authorized budget for the projects needs to be reconciled as per the below table.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Original Authorization

New Authorization

Change

3269

Precinct 3 Community Center Audio Visual Upgrades

$294,608

$369,608

$75,000

3269

Trini Mendenhall Community Center Improvements

$1,485,000

$2,500,000

$1,015,000

3269

Precinct 3 Covered Materials Storage Bins

$1,024,892

$600,000

($424,892)

3269

Precinct 3 Cypress Camp Heavy Equipment Covered Parking

$275,000

$196,742

($78,258)

3269

Baytown Soccer Irrigation

$260,000

$125,000

($135,000)

3269

Cypress Camp 3-Acre Land Acquisition

$1,500,000

$0

($1,500,000)

3269

Dumpster at 5707 Louetta Rd

$170,500

$200,855

$30,355

3269

Dyess Park Water Well

$250,000

$312,183

$62,183

3269

Atascocita Community Center Acquisition

$2,500,000

$2,987,747

$487,747

3269

Crosby Camp Upgrade

$70,000

$42,865

($27,135)

3269

George H.W. Community Center ADA Ramp Improvements

$0

$160,000

$160,000

3269

San Jacinto Community Center Renovations

$0

$60,000

$60,000

3269

Vera May Community Center Renovation

$0

$100,000

$100,000

3269

Fuel Station Upgrades

$0

$75,000

$75,000

3269

Security Fencing at Various Locations

$0

$100,000

$100,000

Total

 

$7,830,000

$7,830,000

-

Note: Separate investment memos are being submitted concurrently for Commissioners Court approval for the five new projects listed at the bottom of the memo.

 

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  Choose an item.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): Choose an item.

 

Previous Court Action:

Date

Agenda Item #

Action Taken

2/27/24

397

Request for approval of the Final Investment Memo for the Precinct 3 Community Center Audio Visual Upgrades project for an initial amount of $294,608 and initial commercial paper funding in the amount of $295,000.

4/23/24

402

Request for approval of the Final Investment Memo for the Trini Mendenhall Community Center Improvements project for an initial amount of $1,485,000 and initial commercial paper funding in the amount of $1,485,000.

6/4/24

413

Request for approval of the Final Investment Memo for the Precinct 3 Covered Materials Storage Bins project for an amount of $1,045,000 and request for approval of commercial paper funding in the amount of $1,045,000.

6/4/24

415

Request for approval of the Final Investment Memo for the Precinct 3 Cypress Camp Heavy Equipment Covered Parking project in the amount of $275,000.

7/15/24

289

Request for approval of a Final Investment Memo for the Baytown Soccer Irrigation project for an initial amount of $260,000 and request for approval of initial non-voted commercial paper funding in the amount of $260,000.

10/29/24

380

Request for approval of a Final Investment Memo for the Cypress Camp 3-Acre Land Acquisition project in the amount of $1,500,000 and request for approval of commercial paper funding in the amount of $1,500,000.

10/29/24

381

Request for approval of a Final Investment Memo for the Dumpster at 5707 Louetta Rd project in the amount of $170,500 and request for approval of commercial paper funding in the amount of $175,000.

12/10/24

480

Request for approval of the Final Investment Memo for the Dyess Park Water Well project for an amount of $250,000 and request for approval of Commercial Paper funding in the amount of $250,000.

2/6/25

283

Request for approval of a Final Investment Memo for the Atascocita Community Center Acquisition and Build-out project, for an amount of $2,500,000 and request for approval of commercial paper funding in the amount of $2,000,000.

2/6/25

285

Request for approval of a Final Investment Memo for the Crosby Camp Upgrade project, for an amount of $70,000, including reallocating $20,108 in allocation from the Precinct 3 Covered Materials Storage Bins project, and request for approval of commercial paper funding in the amount of $70,000, including reallocating $20,000 in budget from the Precinct 3 Covered Materials Storage Bins project.

5/8/25

Current Agenda

Request for approval of a Final Investment Memo for the ADA Ramp Improvements project for an initial amount of $160,000.

5/8/25

Current Agenda

Request for approval of a Final Investment Memo for the San Jacinto Community Center Renovations project for an initial amount of $60,000.

5/8/25

Current Agenda

Request for approval of a Final Investment Memo for the Vera May Community Center Renovations project for an initial amount of $100,000.

5/8/25

Current Agenda

Request for approval of a Final Investment Memo for the Fuel Station Upgrades project for an initial amount of $75,000.

5/8/25

Current Agenda

Request for approval of a Final Investment Memo for the Security Fencing at Various Pct 3 project, for an initial amount of $100,000.

 

Address:

Precinct(s): Precinct 3

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Legal funding compliance confirmed by: N/A

Department Approval by: Jared Bruce, Assistant Director of Budget & Finance

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 4/24/2025

 

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/A