Legislation Details

File #: 26-0872    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 1/27/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request that the County Judge execute an encroachment agreement between Harris County, Texas, a body corporate and politic under the laws of the State of Texas and The City of Houston, a Municipal Corporation situated in Harris, Fort Bend and Montgomery Counties, Texas, for the ITB - Construction of the Downtown Tunnel Flood Mitigation Lift Station for Harris County Precinct 1 (FEMA) project, tract 1, and that the County Judge execute the City of Houston Agreement for Permit for Use and Occupancy of Public Street Right-of-Way with an Annual Fee of $297.90, UPIN 18035MF0X201, Precinct 1.
Attachments: 1. 26-0872-(ILA)18035MF0X201-ITBCODTFMLSforHCP1-P1-2-12-26

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: Not applicable

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): 18035MF0X201

Vendor/Entity Legal Name (if applicable): The City of Houston, a Municipal Corporation situated in Harris,

Fort Bend and Montgomery Counties, Texas

 

 

MWBE Contracted Goal (if applicable): 9.12%

MWBE Current Participation (if applicable): 9.50%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): 90%

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Rate is not 0% and is listed above.

 

Request Summary (Agenda Caption):

title

Request that the County Judge execute an encroachment agreement between Harris County, Texas, a body corporate and politic under the laws of the State of Texas and The City of Houston, a Municipal Corporation situated in Harris, Fort Bend and Montgomery Counties, Texas, for the ITB - Construction of the Downtown Tunnel Flood Mitigation Lift Station for Harris County Precinct 1 (FEMA) project, tract 1, and that the County Judge execute the City of Houston Agreement for Permit for Use and Occupancy of Public Street Right-of-Way with an Annual Fee of $297.90, UPIN 18035MF0X201, Precinct 1.

end

 

Background and Discussion:

The Harris County Downtown Tunnel System connects and provides access to 15 County buildings in Downtown Houston. This project aims to mitigate flooding by installing a large lift station with several sump pumps, powered by an emergency generator on the most vulnerable part of the tunnels, covering the area from the Criminal Justice Center to the Juvenile Justice Center and Civil Court house, to ensure proper flood water removal during extreme weather events. This project will encroach into the public ROW to permanently install 3 manholes and about 28 LF 24" RCP.

 

 

 

 

 

Expected Impact:

Approving this Right of Way Agreement will allow construction activities on this project to start on site as scheduled, thus implementing the flood mitigation plan for the Downtown Tunnel System. The large lift station will ensure proper flood water removal during extreme weather events.

 

 

Alternative Options:

If this agreement is not approved, the contractor MC2 Civil, LLC will not be permitted to mobilize on site, and the project schedule will be delayed.

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

9/18/2025

25-5962

Request for approval of an award on the basis of low bid to MC2 Civil, LLC in the amount of $3,194,500 for construction of the Downtown Tunnel Flood Mitigation Lift Station for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250131), MWBE Contracted Goal: 9.12%.

5/8/2025

25-2906

Transmittal by the office of the Purchasing Agent of a project scheduled for advertisement for construction of the downtown tunnel flood mitigation lift station for Precinct 1.

 

Location:

Address (if applicable): 201 Caroline St. Houston, TX 77002

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper 3259

$

$297.90

$297.90

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$297.90

$297.90

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$297.90

$297.90

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 2/12/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Dr. F. Mike Etienne, Chief of Planning and Development Services, Office of the County Engineer

 

Attachments (if applicable): City of Houston Agreement for Permit for Use and Occupancy of Public Street Right-of-Way; Exhibit Maps