File #: 25-0709    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/21/2025 In control: Commissioners Court
On agenda: 2/6/2025 Final action: 2/6/2025
Title: Request for approval of an amendment to an agreement with Freese and Nichols, Inc., in the amount of $394,338, to provide additional design, bidding, and construction phase engineering services in support of Poor Farm Ditch Conveyance Improvements on HCFCD Unit D111-00-00 (Brays Bayou Watershed, Bond ID C-12, Project ID D111-00-00-C002, Agreement No. 2023-07, Precinct 1, MWBE Contracted Goal: 15.48%, MWBE Current Participation: 15.48%).
Attachments: 1. 020625 AGMT FNI 2023-07 PCT 1 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): D111-00-00-C002

Vendor/Entity Legal Name (if applicable): Freese and Nichols, Inc.

 

MWBE Contracted Goal (if applicable): 15.48%

MWBE Current Participation (if applicable): 15.48%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with Freese and Nichols, Inc., in the amount of $394,338, to provide additional design, bidding, and construction phase engineering services in support of Poor Farm Ditch Conveyance Improvements on HCFCD Unit D111-00-00 (Brays Bayou Watershed, Bond ID C-12, Project ID D111-00-00-C002, Agreement No. 2023-07, Precinct 1, MWBE Contracted Goal: 15.48%, MWBE Current Participation: 15.48%).

end

 

Background and Discussion:

This Amendment will provide additional efforts for engineering services needed for the completion of design and construction for Poor Farm Ditch Conveyance Improvements project. This project includes design, bidding, and reconstruction of an existing concrete lined channel between Bellaire Boulevard and University Boulevard in the Brays Bayou watershed.

 

Expected Impact:

The project seeks to reduce flood risks and strengthen resiliency in the Brays Bayou watershed by alleviating property and structural damages to the adjacent communities. This project will ensure the channel is brought to design capacity and to continue to provide drainage to approximately 1,330 acres of the developed watershed.

 

Alternative Options:

The alternative to approving this item would be to select another firm for the additional efforts, which would result in significant delays.

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/27/2015

1.e.2.a

ATN

06/23/2015

2.b.1.e

Agreement 2016-07

08/01/2017

2.b.7

Amendment No. 1

06/30/2020

2.a.11

Amendment No. 2

08/29/2023

151

Agreement 2023-07

 

Location: Poor Farm Ditch (D111-00-00)

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$394,338

$394,338

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$394,338

$394,338

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$394,338

$394,338

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 2/6/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 