Legislation Details

File #: 24-4005    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 6/18/2024 In control: Commissioners Court
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Request by the Commissioner of Precinct 1 for approval of a Final Investment Memo for the Precinct 1 FY24-25 General Use CIP project for $12,868,000 and approval of commercial paper funding in the amount of $7,495,000.

Department: Commissioner, Precinct 1

Department Head: Rodney Ellis

 

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Precinct 1 FY24-25 General Use CIP

Project ID (if applicable): N/A

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: Commissioner, Precinct 1

Incremental Authorization Requested: $12,868,000

Total Estimated Project Cost: 15,000,000

 

Request Summary:

title

Request by the Commissioner of Precinct 1 for approval of a Final Investment Memo for the Precinct 1 FY24-25 General Use CIP project for $12,868,000 and approval of commercial paper funding in the amount of $7,495,000.

end

 

Project Description:

This comprehensive project involves four distinct tranches aimed at enhancing infrastructure and operational efficiency across key facilities and services.

This project is divided into four tranches to enhance infrastructure and operational capacity. The first tranche is to purchase new vehicles, including operational ones like tractors and vans, to reduce the fleet's average age. The second tranche focuses on remodeling four cabins and complexes. The third tranche aims to replace HVAC units in some of the community centers to improve energy efficiency and comfort. The final tranche involves replacing fences to maintain security and aesthetics. These investments are essential for improving operational efficiency, safety, and service delivery.

 

Project Scope:

Tranche 1:

Item

Number

Unit Cost

Extended Cost

 Total

 

 

 

 

 

 

Bus

4

$600,000

$2,400,000

$2,400,000

 

Excavator

2

$475,000

$950,000

$950,000

 

Loader

4

$76,250

$305,000

$305,000

 

Mower, Slope

2

$150,000

$300,000

$300,000

 

Multi-Charging Stations

1

$250,000

$250,000

$250,000

 

Sewer Truck

1

$300,000

$300,000

$300,000

 

Skid Loader

6

$81,166

$487,000

$487,000

 

Small Tractor w/ Brush Hog

1

$88,000

$88,000

$88,000

 

SUV

4

$75,000

$300,000

$300,000

 

Sweeper, Truck

1

$343,000

$343,000

$343,000

 

Tank, Water

2

$45,000

$90,000

$90,000

 

Tractor

4

$87,000

$348,000

$348,000

 

Trash Truck

3

$260,000

$780,000

$780,000

 

Truck

26

$59,846

$1,556,000

$1,556,000

 

Vacuum

2

$3,000

$6,000

$6,000

 

Van

4

$50,000

$200,000

$200,000

 

 Total

93

 

 

$8,703,000

 

 

 

 

 

 

 

Tranche 2:

Asset

Project

Cost

Tom Bass I Park

Asbestos abatement and complete remodel of the existing space includes improvements to restrooms, shower, and interior finishes. MEP, Fire Suppression and Security Systems will be brought to code. Roof and gutter system will be refurbished. Plus a 630 SF addition which include space for additional offices and an expansion to the breakroom and shop.

$450,000

Tom Bass II Park

Asbestos abatement and remodel of existing office and shop space including upgrades to shower, restrooms and interior finishes. MEP, Fire Suppression and Security Systems will be compliant with building code. Roof and gutter system will be refurbished.

$350,000

Deussen Park Discovery Cabin

Remodel of existing cabin and an addition to support an expanded mammal room and office space. Remodel improvements to the existing building include insulation at the roof, walls, and floor, new flooring, and additional storage in the mammal room.

$300,000

Sheldon Sports Complex Press Box

 Provide a built-up slab at grade that will lift the first level up. Door, electrical panel and conduit would be raised and interior repainted to support the raised floor. In addition, construction of swale drainage system as diagramed in this report that will carry water away from the building along the perimeter of the ball field.

$100,000

TOTAL

$1,200,000

 

 

 

 

 

Tranche 3:

Location

Item

Cost

Adair Park Community Center

Replace 10 Ton R-22 HVAC Unit

$450,000

Deussen Park Community Center

Replace (3) 10 Ton R-22 HVAC Units

$65,000

Lincoln Park Community Center

Replace (4) 12 Ton R-22 HVAC Units

$100,000

Aquatics Center

Replace (2) Pool Paks (R-22)

$1,500,000

TOTAL

$2,115,000

 

 

Tranche 4:

Location

Item

Cost

Tom Bass III

Fence

$150,000

El Camino Campus

Fence

$350,000

TOTAL

$500,000

 

 

 

 

 

 

 

 

Justification:

This project is divided into four parts to address key operational and infrastructure needs. The first part focuses on acquiring new vehicles and equipment to modernize the fleet, boost efficiency, and accommodate increased service demands. The second part involves renovating and upgrading various facilities to ensure safety, regulatory compliance, and enhanced functionality. The third part targets the replacement of outdated HVAC systems in community centers to improve energy efficiency and comfort for users. The final part is dedicated to replacing fences to maintain security and aesthetic appeal in public areas. These strategic investments are vital for maintaining infrastructure, enhancing service delivery, and supporting the community's evolving needs.

 

Alternatives and Engagement:

Failing to proceed with these four projects would have negative impacts on operational efficiency, infrastructure integrity, and community services. Without modernizing the vehicle fleet, maintenance costs and downtime will increase, leading to reduced operational capacity and slower response times. Neglecting the renovation of facilities will result in deteriorating buildings that fail to meet safety and compliance standards, compromising the usability and safety of these spaces. Not replacing outdated HVAC systems will lead to higher energy costs and uncomfortable conditions for community center users, potentially decreasing community engagement. Finally, without replacing fences, security and aesthetics of public spaces will deteriorate, increasing the risk of vandalism and reducing the community’s sense of safety and pride in their surroundings.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

Estimated Cost

Estimated Completion

Tranche 1

$8,703,000

Q4 FY25

Tranche 2

$1,200,000

Q4 FY25

Tranche 3

$2,115,000

Q4 FY25

Tranche 4

$500,000

Q4 FY25

Contingency

$350,000

 

Total

$12,868,000

-

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

 

Address: Multiple

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$7,495,000

$7,495,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$7,495,000

$7,495,000

$

Total Funding Request

$

$7,495,000

$7,495,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/25/2024

Anticipated Implementation Date (if different from Court date):

Legal funding compliance confirmed by: Paige Abernathy, CAO, 6/17/2024

Department Approval by: George Greanias, COO, CP1, 6/5/2024

OMB CIP Team Approval by: Amiel Chen, OMB, CIP Manager, 6/5/2024

 

Commercial Paper Request (For OMB use only):

Receiving Department: Commissioner, Precinct 1

Project PeopleSoft ID: N/A

CP Series Description: Commercial Paper Series D-3 can be used for (1) construction of public works, (2)the purchase of automobiles, equipment, and machinery, including computers, materials, and supplies for the operation of the County’s precincts and departments (3)Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

 

Commercial Paper is being requested for the Precinct 1 FY24-25 General Use CIP project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means, or pay-as-you-go sources.

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget