Title: Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 4 calendar days, with an addition in the amount of $16,490.40, Job No. 19/0305-3, Precinct 1, (project was awarded prior to launch of County's M/WBE Program).
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 19/0305

Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

 

 

MWDBE Contracted Goal (if applicable): 0%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 4 calendar days, with an addition in the amount of $16,490.40, Job No. 19/0305-3, Precinct 1, (project was awarded prior to launch of County’s M/WBE Program).

end

 

Background and Discussion:

 

The project includes the construction of Tidwell Road 4-Lane Concrete Boulevard and Replace Greens Bayou Bridge. The Change Order includes additional time and cost for the Pedestrian Rail Turn Downs (4 days and $16,490.40) for the Tidwell Project.

 

The additional delays are due to a delay in obtaining the materials to install pedestrian railing turn-downs. This improvement was not part of the original contract documents.

 

Expected Impact:

 

The change allows the Contractor to incorporate a change in scope to the project without penalty associated with the delay.

 

Alternative Options:

 

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/29/2019

20.c.9.b

Contract Award

12/01/2020

1.k.2

Contract Amendment for additional funds and extension of project term

05/16/2023

50

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$16,490.40

$

$

Total Incremental Expenditures

$16,490.40

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1070 - Mobility Fund

$16,490.40

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$16,490.40

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$16,490.40

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: November 14, 2023

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B