File #: 25-2108    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/25/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval of a change in contract with Brice Construction & Design, LLC in connection with Telge Rd Segment 4 - from 1,650-ft North of Louetta Rd to 1,780-ft North of Telge Ranch Rd - 2014, adding 6 calendar days, with an addition in the amount of $24,103.08, Job No. 24/0075-1, UPIN 15104MF0DN02, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 99.71%.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0075, UPIN 15104MF0DN02

Vendor/Entity Legal Name (if applicable): Brice Construction & Design, LLC

 

MWBE Contracted Goal (if applicable): 30%

MWBE Current Participation (if applicable): 99.71%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Brice Construction & Design, LLC in connection with Telge Rd Segment 4 - from 1,650-ft North of Louetta Rd to 1,780-ft North of Telge Ranch Rd - 2014, adding 6 calendar days, with an addition in the amount of $24,103.08, Job No. 24/0075-1, UPIN 15104MF0DN02, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 99.71%.

end

 

Background and Discussion:

Project included the reconstruction of Upgrade Telge Road from 1,650-feet North of Louetta Road to 1,780-ft North of Telge Ranch Road.  Reconstruction includes an upgrade of the roadway from a two-lane asphalt road with open ditches to a 4-lane concrete curb and gutter boulevard with a 32' raised median.  The installation of steel plates over the existing roadside inlets was necessary due to concerns that the inlets were not rated for vehicle loads.  To mitigate the conflict and prioritize the critical path, it was necessary to tap, drill, and remove the unknown gas line.  Additionally, days were added because the critical items on the schedule were impacted by these conflicts.

 

The change in contract includes the following:

                     Furnish, Maintain, Remove Steel Plates                                                                                                                                                    $15,039.70

                     Drill/Tap & remove/Dispose of Unknown gas line                                                                                                                              $9,063.38

 

 

Expected Impact:

This change will allow the Contractor to be properly compensated for the additional work.

Alternative Options:

 

Conduct thorough pre-construction assessments and detailed utility mapping to identify and mitigate potential conflicts early.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/23/2024

353 (24-2353)

Contract Award

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3002

$

$24,103.08

$24,103.08

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$24,103.08

$24,103.08

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$24,103.08

$24,103.08

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 4/10/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architecture Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B