File #: 24-3295    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/23/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding three calendar days, with an addition in the amount of $38,842.00, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 13.78%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 19104MF13401 - Job No. 23/0074

Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC

 

MWDBE Contracted Goal (if applicable): 27.00%

MWDBE Current Participation (if applicable): 13.78%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding three calendar days, with an addition in the amount of $38,842.00, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 13.78%.

end

 

Background and Discussion:

The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of new storm sewer system, roadway paving, channel restoration and desilting.

 

The Change in contract request includes the following:

 

•                     PCO #7 - Drainage ditch P118-31-02 draining in to P118-31-00 - An addition of quantities to existing line items #31- 24-inch Reinforced concrete pipe by 48 liner feet, #47-Grade 1 Riprap by 122.2 square yards since the items overran the original commitment amount. Adding a new line for Remobilization and demobilization and temporary dirt dam and dewatering as per revised design plans. Additional quantities for above line items#31 and #47 and added 1 lumpsum for items #91-Remobilization and demobilization and 1 lumpsum for #92- Temporary dirt dam and dewatering are needed to complete the work as proposed in the revised design plans, for an additional cost of $24,742.00 and 3 days.    

•                     PCO #8 - Construction safety fence - Adding new line item for Construction Safety Fence as per design plans for safety reasons during work progress in the project. Added 3000 linear feet at $4.70 per liner feet of new line item#93- Construction Safety Fence for an additional cost of $14,100.00 and 0 days.

 

 

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation
of structural flood damage to homes in the community. This modification is a step in the process to reduce the
financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial
impact of recovery costs to the Fallbrook, Ridgepoint and Westpoint subdivision homeowners, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Fund, for the Recovery and Resiliency Division subdivision projects with the long-term goal of reducing drainage costs in the future. No impact to staffing anticipated.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it.  However, if not approved, the contractor will not be able to complete the original scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

5/16/2023

23-2912

Award of Construction Contract- Specialty Construction TX, LLC

4/23/2024

24-2186

Change Order Approved

 

Location: Fallbrook, Ridgepoint and Westpoint Subdivisions

Address (if applicable):  N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$38,842.00

$38,842.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$38,842.00

$38,842.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$38,842.00

$38,842.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 04, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)