Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): 19.84%
MWBE Current Participation (if applicable): 20.88%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of amendment No. 1 to an agreement with Lockwood, Andrews & Newnam, Inc., in the amount of $41,173.67, to provide design, bidding, and construction phase engineering services in support of the Lauder Stormwater Detention Basin Phase 2 Compartment 2 on HCFCD Unit P500-06-00 (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E007, CDBG-DR, Agreement No. 2024-68, Precinct 2, MWBE Contracted Goal: 19.84%, MWBE Current Participation: 20.88%).
end
Background and Discussion:
This amendment is required to provide post-construction survey services needed as per the requirements of the District’s Surveying Guidelines and for the successful completion of project construction. This project is a component of the Greens Bayou Mid Reach project intended to mitigate flooding in the watershed. Construction of the Lauder SWDB - Phase 1 was completed in February 2022 under Project ID P500-06-00-E005 and construction of Lauder SWDB - Phase 2, Compartment 1 was completed in March 2025 under Project ID P500-06-00-E006. This project includes construction of the Lauder SWDB - Phase 2, Compartment 2 with the project site being approximately 48 acres of land adjacent to the Greens Bayou. The proposed Compartment 2 will be connected to the existing Compartment 1 with a 72-inch Reinforced Concrete Pipe (RCP) connector pipe through the Sunoco easement. Project is being funded by the 2018 Bond and CDBG-DR program. The Flood Control District will construct the project using funding from the CDBG-DR grant program.
Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Greens Bayou watershed by reducing water surface elevations, providing 262 acre-feet of detention, mitigating future conveyance improvements for tributary channel P138-00-00 and provides a 10-year level of service. The project alone provides interim benefits and reduces flood risks to 29 structures during the 100-year storm event.
Alternative Options:
No Action Alternative would fail to meet the purpose and needs of mitigating flood risk and provide additional system capacity for this Community Development Block Grant Disaster Recovery (CDBG-DR) funded project. Under the No action alternative, area residents would continue to be affected by area flooding.
County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H1: Complete and implement the Flood Resilience Plan.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
10/29/2024 |
147. |
Agreement |
Location: N/A
Address (if applicable):
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
4.a.3 - Engineering Services |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Bonds |
$ |
$41,173.67 |
$41,173.67 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$41,173.67 |
$41,173.67 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$41,173.67 |
$41,173.67 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 12/3/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Agreement