Legislation Details

File #: 25-1487    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/6/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval of a change in contract with Southwest Signal Supply, Inc., in connection with final construction of Traffic Signal and Intersection Improvements - West Little York Road at Plantation Crest Drive - 2022, adding 67 calendar days, with an addition in the amount of $19,846.47, Job No. 21/0369-1, UPIN 23104MF2PQ01, Precinct 4, MWBE Contracted Goal: 17.50%, MWBE Current Participation: 98.56%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0369, UPIN 23104MF2PQ01

Vendor/Entity Legal Name (if applicable): Southwest Signal Supply, Inc.

 

MWBE Contracted Goal (if applicable): 17.50%

MWBE Current Participation (if applicable): 98.56%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Southwest Signal Supply, Inc., in connection with final construction of Traffic Signal and Intersection Improvements - West Little York Road at Plantation Crest Drive - 2022, adding 67 calendar days, with an addition in the amount of $19,846.47, Job No. 21/0369-1, UPIN 23104MF2PQ01, Precinct 4, MWBE Contracted Goal: 17.50%, MWBE Current Participation: 98.56%.

end

 

Background and Discussion:

The project involves constructing a new traffic signal system to replace the existing stop sign control at the 4-legged intersection of West Little York Road and Plantation Crest Drive.  This system will feature mast arm poles, ADA-compliant ramps, actuated pedestrian push buttons, pedestrian luminaires, median nose enhancements, and updated pavement markings.

Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.

 

-                     PCO - 1 10 additional days due to numerous utility conflicts on-site, the contractor utilized hydro excavation to expose the utilities.

-                     PCO - 2 An additional 14 days are granted due to Hurricane Beryl, during which the contractor was on-site replacing, repairing, and restoring traffic signals for the Harris County maintenance group.

-                     PCO - 3 Additional 7 days for approval to substitute Bid item# 160 Com Box with alternate fiber pull box (Graybar # AFL FCV-2-E-15).

-                     PCO - 4 Additional 10 days for processing and approval of RFI #6 to increase the footage of bid item #476, 12 Strand Fiber Drop Cable, from 180' to 548'.

-                     PCO - 5 An additional 5 days are requested for approval to relocate pushbutton #8 on pole #6 to the landing in preparation for future sidewalk installation.

-                     PCO - 6 Additional 3 days for approval of pedestrian signal on pole #2 to be moved to the opposite side of pole due the Center Point pole blocking the view.

-                     PCO - 7 Additional 8 days for approval due to Harris County Traffic maintenance availability for pre turn on and turn on.

-                     PCO - 8 An additional 10 days are requested for approval to determine new foundation locations due to utility conflicts.

-                     PCO - 9 Final Adjustment $19,846.47

 

Expected Impact:

Changes allow for addition of new bid items to complete the project in accordance with the original intent of the project and in compliance with precinct requests.

 

Alternative Options:

Revise original scope of the project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/19/2023

301(23-7456)

Contract Extension

11/12/2024

289 (24-7201)

Substantial Completion

 

Location:

Address (if applicable): West Little York Road at Plantation Crest Drive

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$19,846.47

$19,846.47

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$19,846.47

$19,846.47

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$19,846.47

$19,846.47

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/27/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s form 1258B