Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 20104MF1BH01
Vendor/Entity Legal Name (if applicable): Neel Schaffer Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by Neel Schaffer Inc. for Birnam Wood Blvd Segment 2 - from south of J109-01-01 to Cypresswood Drive - 2019, 20104MF1BH01, Precinct 3.
end
Background and Discussion:
The County seeks to facilitate the re-design of the roadway extension of Birnam Wood Boulevard, from south of J109-01-01 to Cypresswood Drive. Upgrading the existing roadway from a 2-lane concrete half boulevard section to a 4-lane concrete curb and gutter boulevard with 32 foot raised median and improved drainage. Study Report has been finalized and is ready for approval.
Expected Impact:
The project will improve the roadway and drainage conditions within this segment of Birnam Wood Boulevard. Neel Schaffer Inc. will be able to proceed with Design Phase once the study report is approved finalizing Study Phase.
Alternative Options:
If not approved, consultant will not be able to proceed with Design Phase tasks and may lead to project delays.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
11/10/2020 |
P.2, 1.g.5 |
Recommendation that the County Judge execute amendments/agreements with: Neel-Schaffer, Inc., in the amount of $249,304 and approval of funds not to exceed $695,886, for engineering services for improvements to Birnam Wood Boulevard, Segment 2 from south of J109-01-01 to Cypresswood Drive in Precinct 4 (UPIN 20104MF1BH01). |
11/15/2022 |
#44 |
Contract - Amendment. Request for approval to execute an amendment with Neel Schaffer, Inc. in the amount of $252,957.00 for Professional Engineering Services to provide improvements to Birnam Wood Boulevard Segment 2 - from south of J109-01-01 to Cypresswood Drive, UPIN 20104MF1BH01, Precinct 3, MWDBE Current participation 4.95%. |
Location:
Address (if applicable): for Birnam Wood Blvd Segment 2 - from south of J109-01-01 to Cypresswood Drive
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: February 27, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department
Attachments (if applicable): Study Report