Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $39,317.60, Job No. 21/0059-9, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 21/0059, UPIN 17102MF0MV01

Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $39,317.60, Job No. 21/0059-9, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

end

 

Background and Discussion:

Project includes the reconstruction of approximately 1.85 miles of Crosby Lynchburg Road (FM 2100) from Magnolia Drive south to Lochness Drive and includes the widening of the bridge over HCFCD Channel G103-05.

 

Change includes:

-                     Per field condition, remove the previously installed TY E Inlet at Sta. 100+76 (Sheet 93), extend the 24-IN RCP by 95 LF to the South, and reinstall and convert the inlet to a MOD TY A inlet in the CL 3 limits. $19,909.74 - 0 days

-                     There are existing utility poles with unstable condition and unclaimed which need to be removed. $10,381.49 - 0 days.

-                     Per field condition, Convert the existing TY E Inlet at Sta. 50+63 LT (CL 3 Limits) to a storm manhole, extend 8 LF of 24-IN RCP and add 1 - 24" SET on the project. $4,325.23 - 0 days.

-                     Offsite drainage swale that has been blocked by finish grading. After the re-evaluation and to eliminate the standing water in this area, it was determined that the offsite drainage needs to be connected to storm system. $10,353.84 - 0 days.

-                     The approved Reinforced Concrete Box (RCB) Lay Schedule provided for the installation of transition RCB with manholes and RCB with manholes in lieu of eight (8) planned junction boxes. The transition RCB with manholes and RCB with manholes function the same as a junction box and EOR confirmed no adverse impact on the storm system in result of this change. Also, this change will improve production rate of the project and saved some amount to HC. - ($5,652.70) - 0 days.

 

Expected Impact:

The changes ensure the project's completion according to its original intent and in compliance with precinct requests.

 

Alternative Options:

Continue with the project in accordance with the original scope.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/27/2021

21-1745

Contract Award

05/24/2022

22-3211

Contract Amendment for additional funds

08/02/2022

22-4566

Contract Amendment for additional funds and extension of project term

09/27/2022

22-5814

Contract Amendment for additional funds and extension of project term

02/21/2023

23-1006

Contract Amendment for additional funds and extension of project term

03/14/2023

23-1746

Contract Amendment for additional funds and extension of project term

08/08/2023

23-4426

Contract Amendment for additional funds and extension of project term

01/30/2024

24-0631

Contract Amendment for additional funds and extension of project term

01/30/2024

24-0632

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precincts 2 & 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund 3109

$

$39,317.60

$39,317.60

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$39,317.60

$39,317.60

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$39,317.60

$39,317.60

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 06, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department