Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): UPIN - 23103MF2RP01
Vendor/Entity Legal Name (if applicable): B2Z Engineering LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with B2Z Engineering LLC for professional services regarding construction materials testing for project Sidewalk - N. Eldridge Pkwy - 2022, Job No. 24/0224, UPIN 23103MF2RP01, Precinct 3.
end
Background and Discussion:
This project contains a 5’ wide concrete sidewalk along N. Eldridge Pkwy and West Rd near Hargove Elementary School. The project is funded through CDBG grant by HCD. This project consists of furnishing all materials, labor, supervision, equipment, and incidentals to construct 5-foot-wide concrete sidewalks. Items of work include, but are not limited to, roadway excavation, removal & relocation of signs, removal of existing concrete pavement, concrete driveways, curb ramp, concrete curb, guardrail, traffic control, site restoration and clean-up. All work shall be performed in accordance with the specifications, construction drawings, any applicable local, state and federal codes, ordinances and regulations. All pedestrian facilities shall be ADA compliant. This project will be federally funded by the U.S. Housing and Urban Development Department (HUD) through the Harris County Community Services Department (HCCSD). Applicable requirements include, but are not limited to, compliance with Davis-Bacon and Related Acts, Fair Labor Standards, Equal Employment Opportunity, Affirmative Action, Section 3 of the HUD Act of 1968, and contracting with small, minority and disadvantaged firms, as detailed in the project manual.
Expected Impact:
Improving the pedestrian facilities will ensure reliable and safe route of transportation to residents of the Harris County.
Alternative Options:
Construction materials testing is required by state law.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
12/13/2022 |
52 |
Consultant agreement for Survey |
Location:
Address (if applicable): Dula Lane
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
Professional Services - CMT |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: October 8th, 2024
Anticipated Implementation Date (if different from Court date):N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Cassandra Green, P.E., Director of Technical Services, Harris County Engineering Department
Attachments (if applicable): N/A