Primary Department: Commissioner, Precinct 4
Primary Department Head/Elected Official: Commissioner Lesley Briones
Managing Department: Commissioner, Precinct 4
Managing Department Head/Elected Official: Commissioner Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Precinct 4 Fonteno Command Center Hardware
Project ID (if applicable): FONTENO_CMDCTR
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $140,000
Total Estimated Project Cost: $140,000
Request Summary:
title
Request for approval of a Final Investment Memo for the Precinct 4 Fonteno Command Center Hardware project, for an amount of $140,000, and request for approval of commercial paper funding in the amount of $140,000.
end
Project Description:
The Precinct 4 Fonteno Center Hardware project aims to install a multi-functional command center for Precinct 4 staff that can support disaster response operations while maintaining its role as a community programming space throughout the year. The upgraded room will feature modern AV technology, including multiple screens with diverse inputs for displaying news, dashboards, weather radars, and press conferences, as well as enhanced hybrid meeting capabilities. All existing functionality-such as microphones, speakers, music playback, and constituent-use programming-will be preserved and improved. The project also includes installing five docking stations in the adjacent room to support staff during emergency operations. Additionally, secure charging lockers will be installed at each community center, allowing staff to charge devices during power outages or disasters safely.
Anticipated Project Expenditures and Timeline:
|
Unit Type |
Unit Count |
Unit Price |
Total |
Estimated Completion |
|
ViewSonic 98" 4K UHD Wireless Presentation Display |
1 |
$ 7,233 |
$ 7,233 |
April 2026 |
|
LG 86" 3840 x 2160 UHD Commercial LED Display |
4 |
$ 2,388 |
$ 9,552 |
April 2026 |
|
Chief TEMPO FP WALL MOUNT SYSTEM |
5 |
$ 1,077 |
$ 5,385 |
April 2026 |
|
Barco CLICKSHARE C-10 (2B) |
4 |
$ 1,833 |
$ 7,332 |
April 2026 |
|
AVPro Edge 4K HDMI Multiview/Tiling processor |
1 |
$ 1,524 |
$ 1,524 |
April 2026 |
|
Visionary Solutions A/V Encoder (Wall Plate) |
1 |
$ 2,128 |
$ 2,128 |
April 2026 |
|
Visionary Solutions A/V Decoder |
8 |
$ 1,365 |
$ 10,920 |
April 2026 |
|
Visionary Solutions A/V Encoder |
10 |
$ 1,370 |
$ 13,700 |
April 2026 |
|
Shure SLX-D Digital Wireless Microphone System |
2 |
$ 1,677 |
$ 3,354 |
April 2026 |
|
QSC Unified Core with 8 local audio I/O channels |
1 |
$ 2,968 |
$ 2,968 |
April 2026 |
|
QSC Touch Controller, Mount, and Cable |
1 |
$ 4,012 |
$ 4,012 |
April 2026 |
|
QSC Q-SYS PoE bridging endpoint for AV-to-USB Bridging |
1 |
$ 2,083 |
$ 2,083 |
April 2026 |
|
Netgear M4250-26G4XF-POE+MANAGEDSWITCH |
1 |
$ 2,839 |
$ 2,839 |
April 2026 |
|
Mid Atlantic AV Rack |
1 |
$ 2,717 |
$ 2,717 |
April 2026 |
|
Shipping & Installation |
1 |
$ 14,857 |
$ 14,857 |
April 2026 |
|
Drawings |
1 |
$ 1,428 |
$ 1,428 |
April 2026 |
|
Plenum Cabling and Duplex Electrical |
1 |
$ 2,293 |
$ 2,293 |
April 2026 |
|
Dedicated Electric for AV Rack |
1 |
$ 1,100 |
$ 1,100 |
April 2026 |
|
Logi Rally Bar and Tap Bundle |
1 |
$ 4,056 |
$ 4,056 |
April 2026 |
|
Cellphone/Tablet Charging Locker & Shipping |
12 |
$ 2,414 |
$ 28,968 |
April 2026 |
|
HP Elite 800 G9 Mini Desktop Computer |
1 |
$ 1,440 |
$ 1,440 |
April 2026 |
|
Subtotal |
|
|
$ 129,889 |
|
|
Contingency |
|
|
$ 10,111 |
|
|
Total |
|
|
$ 140,000 |
|
Justification & Alternatives:
This project is essential to strengthening Harris County Precinct 4’s operational resilience during emergencies while maximizing the year-round value of existing community spaces. By transforming the Discovery Room at Fonteno SEC into a functional command center, we ensure that critical staff have a reliable, generator-powered location to coordinate responses, access live information feeds, and host hybrid meetings during disasters. Upgrading outdated technology improves constituent programming quality while enabling rapid disaster readiness without compromising day-to-day use. Additionally, the installation of secure charging lockers at each community center provides frontline staff with safe, reliable access to power during outages, allowing centers to serve as trusted hubs for continuity of operations. The enhancements support both emergency preparedness and long-term community engagement, making this a smart, mission-aligned investment for the county.
No alternative can provide comparable benefits or reliability. If this project does not receive funding, several lower-cost alternatives may be considered to maintain a degree of disaster readiness and programming support. One option is a minimal upgrade approach that focuses only on replacing outdated projectors and installing limited hybrid meeting capabilities, though this would fall short of the multi-screen, multi-input flexibility required during emergencies. Another alternative is the use of temporary, portable AV equipment that can be deployed in the Discovery Room during disasters, but this introduces logistical challenges and reduces operational reliability. Precinct 4 could also consider designating a different facility as a centralized command center; however, this may limit local responsiveness for the Fonteno area. A virtual command structure, relying solely on remote coordination via Teams or Zoom, could reduce costs but would be vulnerable to power or internet outages.
Anticipated Impact on Other Funds (If Applicable):
|
Fund Code |
Description |
Estimated Cost |
Funding Method (Existing or Future Budget Request Required) |
Estimated Date of Needs |
|
|
|
$- |
|
- |
|
|
|
$- |
|
- |
|
Total |
|
$- |
|
- |
County Strategic Plan Goal: Choose an item.
County Strategic Plan Objective: Choose an item.
Justice/Safety Initiative (Goal 1): Choose an item.
Infrastructure Initiative (Goal 2): Choose an item.
Economy Initiative (Goal 3): Choose an item.
Health Initiative (Goal 4): Choose an item.
Climate/Resilience Initiative (Goal 5): Choose an item.
Housing Initiative (Goal 6): Choose an item.
Decision Analysis Matrix Score (rubric on last page):
Previous Court Action:
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
|
|
|
|
|
|
|
|
Address: 6600 Bissonnet St, Houston, TX 77074
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
|
|
|
|
|
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request |
|
|
Commercial Paper |
$ |
$140,000 |
$140,000 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$140,000 |
$140,000 |
$ |
|
Total Funding Request |
$ |
$140,000 |
$140,000 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 8/26/2025
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 8/14/2025
Department Approval by: Jonathan Castrejon, Director of Finance, June 29th, 2025
OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 8/15/2025
________________________________________
Commercial Paper Request (For OMB use only):
Receiving Department: Commissioner, Precinct 4
Project PeopleSoft ID: FONTENO_CMDCTR
CP Series Description: Commercial Paper Series D-3 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).
Commercial Paper is being requested for the Precinct 4 Fonteno Command Center Hardware project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.
Note: Commercial Paper is issued in increments of $5,000 and the excess is not available to be spent by the department