File #: 24-4538    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 7/19/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire two (2) fee simple tracts for the public project known as Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, for the purpose of roadway construction, UPIN 20104MF1BU01, Precinct 3.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

 

Project ID (if applicable): 20104MF1BU01

Vendor/Entity Legal Name (if applicable): Not applicable

 

MWDBE Contracted Goal (if applicable): Not applicable

MWDBE Current Participation (if applicable): Not applicable

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire two (2) fee simple tracts for the public project known as Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, for the purpose of roadway construction, UPIN 20104MF1BU01, Precinct 3.

end

 

Background and Discussion:

This project consists of upgrading Shaw Rd from Northpointe Blvd. to Boudreaux Rd from partially half blvd, partially two lane asphalt to four lane concrete with curb and gutter 32' median within 100' of ROW with the following traffic signals: Sunset Canyon Dr. There is one outfall with inline detention and pond that will outfall to the Northpointe WCID detention system. The acquisition of the two parcels in this request are for the detention pond included in the improvements of this project.

 

Expected Impact:

The approval of this request will ensure the completion of the project Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019.

 

Alternative Options:

If this request is not approved, it will cause delay in the completion of the project Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019.

 

 

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): None

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): 18334 Shaw Road & 1000 Sunset Canyon Drive, Tomball, Texas 77429

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

 

 

 

 

Anticipated Court Date: August 6, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Trevor Smith, Assistant Interim Director, Real Property Division

 

Attachments (if applicable): Findings and Declarations; Survey Descriptions and Maps