File #: 25-4204    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/26/2025 In control: Commissioners Court
On agenda: 7/10/2025 Final action: 7/10/2025
Title: Request for approval of an amendment to an agreement with IDCUS Inc in the amount of $86,224.75 for additional Engineering Services for the Hufsmith-Kohrville Road Segment 4 - from 500' north of Holderreith Road to Mahaffey Road - 2015 project, UPIN 15104M23NP04, Precinct 3, MWBE Contracted Goal: 12.69%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 15104M23NP04

Vendor/Entity Legal Name (if applicable): IDCUS Inc

 

MWBE Contracted Goal (if applicable): 12.69%

MWBE Current Participation (if applicable): N/A                     

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A                     

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with IDCUS Inc in the amount of $86,224.75 for additional Engineering Services for the Hufsmith-Kohrville Road Segment 4 - from 500' north of Holderreith Road to Mahaffey Road - 2015 project, UPIN 15104M23NP04, Precinct 3, MWBE Contracted Goal: 12.69%.

end

 

Background and Discussion:

 

The County executed an agreement for Professional Engineering Services with IDCUS Inc in 2023 and now seeks to amend the agreement for the second time.  This amendment will facilitate the prime consultant to provide the additional design services needed for new drainage direction to utilize the City of Tomball masterplan basin. The general scope of this project consists of Hufsmith-Kohrville Road from 500' north of Holderrieth Road to Mahaffey Road, from existing 2-lane asphalt roadway to a 4-lane concrete curb and gutter boulevard, with 32' raised median, within a 100' ROW. The amendment is for $148,340.91 for the work to utilize the City of Tomball Basin.  The current contract includes fees ($62,224.75) associated with the original scope of a new Harris County Basin.  This fee will be reallocated towards the new fee and reduce the total funding code request to $86,224.75.

 

 

 

 

Expected Impact:

 

 The approval of this amendment will allow the Prime consultant to provide the additional Engineering Services needed for the project. The completion of design and construction of the subject project will improve the existent traffic conditions for the community in the specified area.

 

 

Alternative Options:

 

The alternative is to move forward with the current drainage scope that will include acquiring, constructing and maintaining a separate basin for Harris County.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10.14.2014

1.e.3.h p9

IDC, Inc., for engineering services in connection with road improvements to Hufsmith-Kohrville Road, Segment 4 from north of Holderrieth Road to Willow Creek Estates Drive in Precinct 4 (UPIN 15104M23NP04).

5.16.2023

48 p6

 Request for approval to execute an amendment with IDCUS, Inc. in the amount of $205,162.03 for Professional Engineering Services to provide improvements to Hufsmith-Kohrville Road Segment 4, UPIN 15104M23NP04, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

 

 

 

 

Location:

Address (if applicable): Hufsmith-Kohrville Rd & Holderrieth Rd

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$86,224.75

$ 86,224.75

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$86,224.75

$ 86,224.75

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$86,224.75

$86,224.75

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 7/10/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Truitt Rounsavall, P.E., PMP, MBA, LSSBB, Director of Capital Project Infrastructure, Office of the County Engineer.

 