Legislation Details

File #: 24-7496    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/24/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding 1 calendar day, with no change in the amount, Job No. 23/0074-05, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 10.71%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 19104MF13401 - Job No. 23/0074

Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC

 

MWDBE Contracted Goal (if applicable): 27.00%

MWDBE Current Participation (if applicable): 10.71%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding 1 calendar day, with no change in the amount, Job No. 23/0074-05, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 10.71%.

end

 

Background and Discussion:

The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, roadway paving, channel restoration and desilting.

 

The Change in contract is needed to add new items to reconcile new line items with the underrunning items of the contract. The following quantity adjustments are required:

 

•                     New line items #101 and 102 need to be added for an additional amount of $2,658.00 and 1 day.

 

•                     To offset, underrunning line item #82 will be decreased for a deduction in the amount of $2,658.00.

 

•                     The above additions and deductions resulted in a net addition to the contract in the amount of $0.00 and 1 calendar day.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation
of structural flood damage to homes in the
Fallbrook, Ridgepoint and Westpoint subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it.  However, if not approved, the contractor will not be able to complete the scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/16/2023

23-2912

Award of Construction Contract- Specialty Construction TX, LLC

04/23/2024

24-2186

Contract Amendment (23/0074-1) for additional funds and extension of project term

06/04/2024

24-3295

Contract Amendment (23/0074-2) for additional funds and extension of project term

07/15/2024

24-4056

Contract Amendment (23/0074-3) for extension of project term

11/12/2024

24-7214

Contract Amendment (23/0074-4) for additional funds and extension of project term

 

Location: Fallbrook, Ridgepoint and Westpoint Subdivisions, Fallbrook, Texas

Address (if applicable):  N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: December 10, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)