Primary Department: Universal Services
Primary Department Head/Elected Official: Sindhu Menon, Executive Director
Managing Department: Universal Services
Managing Department Head/Elected Official: Sindhu Menon, Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Texas Wide Area Radio Network Modernization and Upgrade
Project ID (if applicable): NI059
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $73,282,845
Total Estimated Project Cost: $73,282,845
Request Summary:
title
Request for approval of the Final Investment Memo for the Texas Wide Area Radio Network Upgrade project for a total authorization of $73,282,845.
.end
Project Description:
Harris County owns and operates one of the largest Public Safety Regional Communications Systems in the Nation. The current infrastructure has been in service since the early 2000’s. This project is part of a 6-year (FY 2027 - FY 2032) system upgrade of the public safety radio infrastructure that includes critical base stations and consoles. By upgrading to state of the art infrastructure equipment and the overall radio network, Harris County will be able to provide continued support, ensure interoperability, and reduce the maintenance and support costs associated with legacy end of life equipment.
This project will provide key infrastructure upgrades to all 31 Harris County owned mission-critical radio tower sites, and all Harris County supported wireline dispatch positions across Harris County Public Safety agencies. Additionally, this funding will provide continuous infrastructure upgrades to the entire radio system completed on a bi-yearly basis without service interruption or downtime.
This project is necessary to continue to support and advance interoperable critical communications across all Law, Fire, EMS, and Emergency Response services within Harris County and throughout the entire TxWARN (Texas Wide Area Radio Network) radio system.
Anticipated Project Expenditures and Timeline:
|
Project Scope Breakdown |
Vendor Cost |
Contract Resources |
Subtotal |
Contingency |
Grand Total |
|
FY 2027 |
$11,700,000 |
$400,000 |
$12,100,000 |
$585,000 |
12,685,000 |
|
FY 2028 |
$10,500,000 |
$400,000 |
$10,900,000 |
$525,000 |
11,425,000 |
|
FY 2029 |
$12,400,000 |
$400,000 |
$12,800,000 |
$620,000 |
13,420,000 |
|
FY 2030 |
$13,300,000 |
$400,000 |
$13,700,000 |
$665,000 |
14,365,000 |
|
FY 2031 |
$9,507,471 |
$400,000 |
$9,907,471 |
$475,374 |
10,382,845 |
|
FY 2032 |
$10,100,000 |
$400,000 |
$10,500,000 |
$505,000 |
11,005,000 |
|
Total |
$67,501,471 |
$2,400,000 |
$69,907,471 |
$3,375,374 |
73,282,845 |
Justification & Alternatives:
The project is a requirement to continue uninterrupted operation of a vital radio communication system. The TxWARN system functions continuously, 24 hours a day, seven days a week, supporting public safety and disaster response across interagency networks. It serves a substantial geographic area, encompassing 40+ counties in East Texas. Maintaining and upgrading this infrastructure is essential for reliable communication during emergencies and for protecting communities throughout the region.
Alternatives for this project involve utilizing systems from other manufacturers, which would operate independently and result in the loss of direct communications with counties currently integrated with the Motorola platform. Non-funding of this project will result in operational instability, potential downtime, and vulnerabilities within a vital radio communication system that is utilized by law enforcement and all emergency response services within Harris County.
Anticipated Impact on Other Funds (If Applicable):
|
Fund Code |
Description |
Estimated Cost |
Funding Method (Existing or Future Budget Request Required) |
Estimated Date of Needs |
|
|
|
$- |
|
- |
|
|
|
$- |
|
- |
|
Total |
|
$- |
|
- |
County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): R3: Strengthen the County’s emergency response function.
Housing Initiative (Goal 6): N/A
Previous Court Action:
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
|
|
|
|
Address: Multiple
Precinct(s): Countywide
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
|
|
|
|
|
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request |
|
|
Certificate of Obligation |
$ |
$12,685,000 |
$12,685,000 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$12,685,000 |
$12,685,000 |
$ |
|
Total Funding Request |
$ |
$12,685,000 |
$12,685,000 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 11/19/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Legal funding compliance confirmed by: Paige Abernathy, First Assistant County Attorney-Legal Operations, 11/9/2026
Department Approval by: Meg Philip, Chief Financial Officer, Universal Services, 11/10/2026
OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 11/10/2026
________________________________________
Commercial Paper Request (For OMB use only):
Receiving Department: N/A
Project PeopleSoft ID: N/A
CP Series Description: N/A
OMB Financial Management contact: N/A