Legislation Details

File #: 24-4113    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 7/2/2024 In control: Commissioners Court
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Request for approval to execute an agreement with OMEGA Engineers Inc in the amount of $62,634 for Construction Phase Services in connection with Carpenters Bayou - Trails and Pedestrian Bike Bridge - 24/0107, UPIN 19101MF0YC01, Precincts 1 and 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Attachments: 1. 24-4113-Consultant-UPIN 19101MF0YC01 Carpenters Bayou - Trails and Pedestrian Bike Bridge - OMEGA Engineers Inc

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 19101MF0YC01

Vendor/Entity Legal Name (if applicable): OMEGA Engineers Inc

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with OMEGA Engineers Inc in the amount of $62,634 for Construction Phase Services in connection with Carpenters Bayou - Trails and Pedestrian Bike Bridge - 24/0107, UPIN 19101MF0YC01, Precincts 1 and 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

The project is to construct a 10 ft wide trail along Carpenters Bayou between Flintcrest Dr and Wallisville Rd. Install prefabricated pedestrian bridge over Carpenters Bayou near Wallisville Rd. Constructing 8 ft sidewalk along Wallisville Rd, between Beltway 8 and Hidden Park Dr.

 

Expected Impact:

This action will allow OMEGA Engineers Inc to support the construction of the project.

 

Alternative Options:

If no action is taken, the engineer of record will not be accessible for support through the construction of the

project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

4-10-2018

1.f.6

ATN for Professional Services

2-26-2019

1.f.1

Professional Services Agreement

10-13-2020

1.g.1

Amendment #1

 

Location: Wallisville Rd, between Beltway 8 and Hidden Park Dr.

Address (if applicable):

Precinct(s): Precincts 1 & 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$62,634

$62,634

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$62,634

$62,634

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$62,634

$62,634

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: July 15, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department:  Erwin Burden, PE, CFM, Senior Director of Capital Project Infrastructure, HCED

 

Attachments (if applicable): Contract